Summary of Costs and Time occupied in carrying out various surveys,

1. Ordnance Survey of Central and Western portion of the City :-

Area surveyed, 72 acres.

Time occupied, 358 days.

Total cost, $4,654

Average cost per acre, $64

2. Survey of Shaukiwan :

Area surveyed, 42 acres.

Time occupied, 121 days.

Total cost, $1,726

Average cost per acre, $42

3. Ordnance Survey of Peak :—

Area surveyed, 55 acres.

Time occupied, 248 days.

Total cost, $3,110

Average cost per acre, $56.50

4. New Territories, Village Surveys:

Number of villages surveyed, 63

Time occupied, 244 days.

Number of houses, 3,297

Total cost, $2,882

5. Survey of Aberdeen Village and cultivation :—

Area surveyed, 27 acres.

Time occupied, 75 days.

Total cost, $974

Average cost per acre, $36

6. New Territories, Village Surveys (under contract) :—

Number of villages surveyed, 17

Time occupied, 210 days.

Number of houses, 2,315

Total cost, $1,877