260 Land, Public Works and Utilities
five-yearly interim reviews were completed in early 1999 and late 2003, respectively. The agreements require each company to seek the approval of the Government for certain aspects of their financial plans, including projected tariff levels. The agreements do not grant the companies any exclusive rights. They are not franchises, nor do they define a supply area for either company or exclude new entrants to the market.
Electricity for HEC's supply areas is supplied from the Lamma Power Station. At year-end, total installed capacity (i.e. rated power output of generators) at the Lamma Power Station was 3 420 megawatts (MW). In May 2000, the Government approved HEC's new power station at the Lamma Extension and the installation of the first 300MW gas combined-cycle generator. The unit was scheduled to be commissioned in 2004. Subsequent to the review conducted at end-2003, the Government agreed with HEC's proposal to defer the commissioning of the unit to 2006. HEC's transmission system operates at 275 kilovolts (kV), 132kV and 66kV and distribution is effected mainly at 22kV, 11kV and 380 volts.
The Castle Peak Power Company Limited (CAPCO), which is 60 per cent owned by ExxonMobil Energy Limited (formerly known as Exxon Energy Limited) and 40 per cent by CLP Power, supplies electricity to CLP Power from its Black Point (1 875MW), Castle Peak (4 108MW) and Penny's Bay (300MW) power stations, with the total installed capacity being 6 283MW. Two more 312.5MW generators are scheduled to be commissioned at the Black Point power station during 2005-06.
CLP Power wholly owns the associated transmission and distribution systems. Its transmission system operates at 400kV and 132kV, and distribution is effected mainly at 33kV, 11kV and 380 volts.
The CLP Power and HEC transmission systems are interconnected by a cross- harbour link. This provides emergency back-up and achieves cost savings to consumers through economic energy transfers between the two systems and a reduction in the amount of generating capacity that needs to be kept as spinning reserve against the tripping of other units. The interconnection link currently has a total capacity of 720 megavolt-amperes (MVA) (i.e. 720 000 kilovolt-amperes (KVA)).
CLP Power's transmission system is also interconnected with the electricity network in Guangdong Province which facilitates the export and import of electricity to and from the province. The electricity sales to Guangdong are made from existing reserve generating capacity of CLP Power and are governed by an agreement with the Government, under which CLP Power's consumers receive priority of supply and 80 per cent of the profit from the sales.
In 1985, the Hong Kong Nuclear Investment Company Limited (a wholly-owned subsidiary of the CLP Holdings Limited) and the Guangdong Nuclear Investment Company Limited (now wholly owned by the China Guangdong Nuclear Power Holding Company Limited) established the Guangdong Nuclear Power Joint Venture Company Limited, to build and operate the Guangdong Nuclear Power Station at Daya Bay in Guangdong. This station comprises two 984MW pressurised water reactors which went into commercial operation in February and May 1994,
No comments yet.
Private notes are available after approval.