CONTRACT No. 49 OF 1923. CONTRACTORS: MESSRS. KIN LEE & Co.

4th Quarterly Report ending 30th June, 1925.

Laid before the Legislative Council by Command of His Excellency

the Governor on the 24th September, 1925.

Satisfactory progress was being made until the commencement of the present un- settled labour conditions; workmen have left the site and the work is necessarily pro- ceeding very slowly at present.

The brickwork has been completed to the roof level and the tower has been carried up to a few feet higher than roof. The floor to top storey and also the verandah roofs are completed. Steel trusses over Science Block have been fixed and the roof timbering to both N. & S. Blocks is practically finished. Roof tiling has been commenced on the South Block.

The steel roof trusses over Assembly Hall are in position and internal plastering has progressed favourably.

The standard of work is good.

22nd July, 1925.

HAROLD T. CREASY,

Director of Public Works.