Contract time for completion-5 years from the 27th October, 1910.
Contract price,
Cost of Contractor's extras other than those for which provision is made in the Contract,
****
.$2,018,002
Nil.
Total amount of Contract and Extras, ...$2,018,002
Divided into 60 months,
50 months at $33,633,
$ 33,633 per month.
.$1,681,650
Amount earned by Contractor on work actually accomplished including sum retained under the provisions of the Contract in the hands of the Government,
..$1,732,039
15th January, 1915,
W. CHATHAM, Director of Public Works.