STATEMENT TO 31ST DECEMBER, 1914,

(vide pages 10 and Il of Hansard, 23rd February, 1911).

2

No. 1915

Laid before the Legislative Council by Command of His Excellency the Governor, January 21st, 1915.

Contract time for completion-5 years from the 27th October, 1910.

Contract price,

Cost of Contractor's extras other than those for which provision is made in the Contract,

****

.$2,018,002

Nil.

Total amount of Contract and Extras, ...$2,018,002

Divided into 60 months,

50 months at $33,633,

$ 33,633 per month.

.$1,681,650

Amount earned by Contractor on work actually accomplished including sum retained under the provisions of the Contract in the hands of the Government,

..$1,732,039

15th January, 1915,

W. CHATHAM, Director of Public Works.