45
HONGKONG.
TYPHOON REFUGE.
STATEMENT TO 30TH JUNE, 1913,
(vide pages 10 and 11 of Hansard, 23rd February, 1911).
No. 1913
Laid before the Legislative Council by Command of His Excellency the Governor, July 31st. 1913,
Contract time for completion--5 years from the 27th October, 1910.
Contract price,
$2,018,002
Cost of Contractor's extras other than those for which provision is made in the Contract,
Nil.
Total amount of Contract and Extras, ...$2,018,002
Divided into 60 months,
32 months at $33,633,
33,633 per month.
...$1,076,256
Amount earned by Contractor on work actually accomplished including sum retained under the provisions of the Contract in the hands of the Government,
.$1,069,551
10th July, 1913.
W. CHATHAM, Director of Public Works.
No comments yet.
Private notes are available after approval.