Contract time for completion-5 years from the 27th October, 1910.

Contract price,

$2,018,002

Cost of Contractor's extras other than those for

which provision is made in the Contract,

Nil.

Total amount of Contract and Extras, ...$2,018,002

Divided into 60 months,

..$

33,633 per month.

.$ 672,660

20 months at $33,633,....

Amount earned by Contractor on work actually accomplished including sum retained under the provisions of the Contract in the hands of the Government,

$ 558,833

15th July, 1912.

W. CHATHAM,

Director of Public Works.