Contract time for completion-5 years from the 27th October, 1910.
Contract price,
$2,018,002
Cost of Contractor's extras other than those for
which provision is made in the Contract,
Nil.
Total amount of Contract and Extras, ...$2,018,002
Divided into 60 months,
..$
33,633 per month.
.$ 672,660
20 months at $33,633,....
Amount earned by Contractor on work actually accomplished including sum retained under the provisions of the Contract in the hands of the Government,
$ 558,833