1976-1977 — Page 45

Public Works Department Annual Report 工務司署年報 All AI Reviewed

Committee

Building (Alterations, Additions and Improvements) Committee

Fire Services Contractors' Disciplinary Board

4.09

Representative(s)

Government Maintenance Surveyor

Chief Quantity Surveyor

The Government Architects administer the work of the Architectural Divisions with particular regard to control and co-ordination. Government Architect/Administration has particular responsibility for Architectural Divisions II, IV and V and Government Architect/General for Architectural Divisions I and III.

ARCHITECTURAL DIVISIONS

Chief Architects :

Chief Architect, Division I:Edwin WONG, B. Arch. (N.Z.), A.N.Z.I.A., A.R.I.B.A.CHEW King-kwen, A.R.I.B.A. (Acting) Chief Architect, Division IIP. CHUNG Yin-min, Dip. Arch. A.R.I.B.A.F. HO-ASJOE Wai-yiu, B. Arch. (Univ. of Manitoba), A.R.I.B.A., M.R.A.I.C. (Acting) KWAN Sai-chung, B. Arch. (HK), A.R.I.B.A., M.R.S.H. (Acting) Chief Architect, Division IIIJ. LEI Meng-canMAK Shon-sau, B. Arch. (HK), A.R.I.B.A. (Acting) KU To-kan, Dip. Arch., A.R.I.B.A. (Acting) Chief Architect, Division IVMAK Shon-sau, B. Arch. (HK), A.R.I.B.A. (Acting)A.M. WAHAB, B. Arch. (HK), M. Arch. (Melbourne), A.R.A.I.A., A.R.I.B.A. (Acting) Chief Architect, Division VCHUI Hay-man, B. Sc. (Hang Chow Christian University, China)(Acting)

4.10

All five Architectural Divisions are engaged on new works and each is headed by a Chief Architect. Divisions I and II are each sub-divided into three groups headed by Senior Architects, each group forming a working team capable of handling the whole process of designing the buildings and preparing the architectural drawings for the projects allocated to them. Each of these groups is allocated the building programme of

To

35

Page 45

Page 46

Edit History

2026-05-12 08:29:38 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Committee Building (Alterations, Additions and Improvements) Committee Fire Services Contractors' Disciplinary Board 4.09 Representative(s) Government Maintenance Surveyor Chief Quantity Surveyor The Government Architects administer the work of the Architectural Divisions with particular regard to control and co-ordination. Government Architect/Administration has particular responsibility for Architectural Divisions II, IV and V and Government Architect/General for Architectural Divisions I and III. ARCHITECTURAL DIVISIONS Chief Architects : Chief Architect, Division I:Edwin WONG, B. Arch. (N.Z.), A.N.Z.I.A., A.R.I.B.A.CHEW King-kwen, A.R.I.B.A. (Acting) Chief Architect, Division IIP. CHUNG Yin-min, Dip. Arch. A.R.I.B.A.F. HO-ASJOE Wai-yiu, B. Arch. (Univ. of Manitoba), A.R.I.B.A., M.R.A.I.C. (Acting) KWAN Sai-chung, B. Arch. (HK), A.R.I.B.A., M.R.S.H. (Acting) Chief Architect, Division IIIJ. LEI Meng-canMAK Shon-sau, B. Arch. (HK), A.R.I.B.A. (Acting) KU To-kan, Dip. Arch., A.R.I.B.A. (Acting) Chief Architect, Division IVMAK Shon-sau, B. Arch. (HK), A.R.I.B.A. (Acting)A.M. WAHAB, B. Arch. (HK), M. Arch. (Melbourne), A.R.A.I.A., A.R.I.B.A. (Acting) Chief Architect, Division VCHUI Hay-man, B. Sc. (Hang Chow Christian University, China)(Acting) 4.10 All five Architectural Divisions are engaged on new works and each is headed by a Chief Architect. Divisions I and II are each sub-divided into three groups headed by Senior Architects, each group forming a working team capable of handling the whole process of designing the buildings and preparing the architectural drawings for the projects allocated to them. Each of these groups is allocated the building programme of To 35 Page 45 Page 46
Baseline (Original)
Committee Building (Alterations, Additions and Improvements) Committee Fire Services Contractors' Disciplinary Board 4.09 Representative(s) Government Maintenance Surveyor Chief Quantity Surveyor The Government Architects administer the work of the Architectural Divisions with particular regard to control and co- ordination. Government Architect/Administration has particular responsibility for Architectural Divisions II, IV and V and Government Architect/General for Architectural Divisions I and III. ARCHITECTURAL DIVISIONS Chief Architects : Chief Architect, Division I: Edwin WONG, B. Arch. (N.Z.), A.N.Z.I.A., A.R.I.B.A. CHEW King-kwen, A.R.I.B.A. (Acting) Chief Architect, Division II P. CHUNG Yin-min, Dip. Arch. A.R.I.B.A. F. HO-ASJOE Wai-yiu, B. Arch. (Univ. of Manitoba), A.R.I.B.A., M.R.A.I.C. (Acting) KWAN Sai-chung, B. Arch. (HK), A.R.I.B.A., (HK), A.R.I.B.A., M.R.S.H. (Acting) Chief Architect, Division III J. LEI Meng-can MAK Shon-sau, B. Arch. (HK), A.R.I.B.A. (Acting) KU To-kan, Dip. Arch., A.R.I.B.A. (Acting) Chief Architect, Division IV MAK Shon-sau, B. Arch. (HK), A.R.I.B.A. (Acting) A.M. WAHAB, B. Arch. (HK), M. Arch. (Melbourne), A.R.A.I.A., A.R.I.B.A. (Acting) Chief Architect, Division V CHUI Hay-man, B. Sc. (Hang Chow Christian University, China) 4.10 (Acting) All five Architectural Divisions are engaged on new works and each is headed by a Chief Architect. Divisions I and II are each sub-divided into three groups headed by Senior Architects, each group forming a working team capable of handling the whole process of designing the buildings and preparing the architectural drawings for the projects allocated to them. each of these groups is allocated the building programme of To 35 Page 45Page 46
2026-05-12 08:29:38 · Baseline
View content

Committee

Building (Alterations, Additions

and Improvements) Committee

Fire Services Contractors'

Disciplinary Board

4.09

Representative(s)

Government Maintenance Surveyor

Chief Quantity Surveyor

The Government Architects administer the work of the Architectural Divisions with particular regard to control and co- ordination. Government Architect/Administration has particular responsibility for Architectural Divisions II, IV and V and Government Architect/General for Architectural Divisions I and

III.

ARCHITECTURAL DIVISIONS

Chief Architects :

Chief Architect, Division I:

Edwin WONG, B. Arch. (N.Z.), A.N.Z.I.A., A.R.I.B.A. CHEW King-kwen, A.R.I.B.A. (Acting)

Chief Architect, Division II

P. CHUNG Yin-min, Dip. Arch. A.R.I.B.A.

F. HO-ASJOE Wai-yiu, B. Arch. (Univ. of Manitoba), A.R.I.B.A.,

M.R.A.I.C. (Acting) KWAN Sai-chung, B. Arch. (HK), A.R.I.B.A.,

(HK), A.R.I.B.A., M.R.S.H. (Acting)

Chief Architect, Division III

J. LEI Meng-can

MAK Shon-sau, B. Arch. (HK), A.R.I.B.A. (Acting) KU To-kan, Dip. Arch., A.R.I.B.A. (Acting)

Chief Architect, Division IV

MAK Shon-sau, B. Arch. (HK), A.R.I.B.A. (Acting) A.M. WAHAB, B. Arch. (HK), M. Arch. (Melbourne), A.R.A.I.A.,

A.R.I.B.A. (Acting)

Chief Architect, Division V

CHUI Hay-man, B. Sc. (Hang Chow Christian University, China)

4.10

(Acting)

All five Architectural Divisions are engaged on new works and each is headed by a Chief Architect. Divisions I and II are each sub-divided into three groups headed by Senior Architects, each group forming a working team capable of handling the whole process of designing the buildings and preparing the architectural drawings for the projects allocated to them. each of these groups is allocated the building programme of