(iii) New Territories

Castle Peak Road Improvement, Castle Peak to Ping Shan - Stage II

Approximate Cost

8,414,238

High Island Roads - Improved Standards

11,002,217

Man Kam To Road Bridge

1,182,279

Hang Hau Road Reconstruction

2,190,451

Construction of High Protective Fenders for the Tsing Yi Bridge

124,774

Kwai Chung Development Area 27, 28 & 29 (Part) - Drainage and roads

7,938,352

Lai Chi Kok Terrace Road

4,100,589

Lai King Low Cost Housing Estate, Stage I Roads & Drainage Works

1,879,522

Roads & Drainage Works for Lai King Public Housing Estate, Stage II

582,056

Lei Muk Shue - Construction of Roads & Drainage Works

1,346,209

Lek Yuen San Tsuen, Construction of Internal Roads & Ancillary Drainage Works

2,676,926

Road improvement for relocation of R.A.F. Facilities from Kai Tak to Sek Kong Village

238,637

Improvement of Luk Keng Road Minimal improvements

280,331

Provision of bus bay and modification of the existing road junction at Castle Peak Road junction with Tai Ho Road

197,837

Desilting Kwai Chung Main Culvert

481,502

Construction of Roads at Tai Po Lot No. 1604 and 1211 Sec. A, B, E and C Tai Po

140,000

Construction of Urn Burial Terraces - Wo Hop Shek Cemetery 8th Contract

528,181

229

Edit History

2026-05-12 09:52:10 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
APPENDIX X - Cont'd. (iii) New Territories Castle Peak Road Improvement, Castle Peak to Ping Shan - Stage II Approximate Cost 8,414,238 High Island Roads - Improved Standards 11,002,217 Man Kam To Road Bridge 1,182,279 Hang Hau Road Reconstruction 2,190,451 Construction of High Protective Fenders for the Tsing Yi Bridge 124,774 Kwai Chung Development Area 27, 28 & 29 (Part) - Drainage and roads 7,938,352 Lai Chi Kok Terrace Road 4,100,589 Lai King Low Cost Housing Estate, Stage I Roads & Drainage Works 1,879,522 Roads & Drainage Works for Lai King Public Housing Estate, Stage II 582,056 Lei Muk Shue - Construction of Roads & Drainage Works 1,346,209 Lek Yuen San Tsuen, Construction of Internal Roads & Ancillary Drainage Works 2,676,926 Road improvement for relocation of R.A.F. Facilities from Kai Tak to Sek Kong Village 238,637 Improvement of Luk Keng Road Minimal improvements 280,331 Provision of bus bay and modification of the existing road junction at Castle Peak Road junction with Tai Ho Road 197,837 Desilting Kwai Chung Main Culvert 481,502 Construction of Roads at Tai Po Lot No. 1604 and 1211 Sec. A, B, E and C Tai Po 140,000 Construction of Urn Burial Terraces - Wo Hop Shek Cemetery 8th Contract 528,181 229
Baseline (Original)
Project APPENDIX X - Cont'd. (iii) New Territories Castle Peak Road Improvement, Castle Peak to Ping Approximate Cost Shan - Stage II 8,414,238 High Island Roads - Improved Standards 11,002,217 Man Kam To Road Bridge 1,182,279 Hang Hau Road Reconstruction 2,190,451 Construction of High Protective Fenders for the Tsing Yi Bridge 124,774 Kwai Chung Development Area 27, 28 & 29 (Part) Drainage and roads 7,938,352 Lai Chi Kok Terrace Road 4,100,589 Lai King Low Cost Housing Estate, Stage I Roads & Drainage Works - 1,879,522 Roads & Drainage Works for Lai King Public Housing Estate, Stage II 582,056 Lei Muk Shue Construction of Roads & Drainage Works 1,346,209 Lek Yuen San Tsuen, Construction of Internal Roads & Ancillary Drainage Works 2,676,926 Road improvement for relocation of R.A.F. Facilities from Kai Tak to Sek Kong Village 238,637 Improvement of Luk Keng Road Minimal improvements << 280,331 Provision of bus bay and modification of the existing road junction at Castle Peak Road junction with Tai Ho Road 197,837 Desilting Kwai Chung Main Culvert 481,502 Construction of Roads at Tai Po Lot No. 1604 and 1211 Sec. A, B, E and C Tai Po 140,000 Construction of Urn Burial Terraces - Wo Hop Shek Cemetery 8th Contract - 528,181 229
2026-05-12 09:52:10 · Baseline
View content

Project

APPENDIX X - Cont'd.

(iii) New Territories

Castle Peak Road Improvement, Castle Peak to Ping

Approximate

Cost

Shan

-

Stage II

8,414,238

High Island Roads

-

Improved Standards

11,002,217

Man Kam To Road Bridge

1,182,279

Hang Hau Road Reconstruction

2,190,451

Construction of High Protective Fenders for the

Tsing Yi Bridge

124,774

Kwai Chung Development Area 27, 28 & 29 (Part)

Drainage and roads

7,938,352

Lai Chi Kok Terrace Road

4,100,589

Lai King Low Cost Housing Estate, Stage I Roads

& Drainage Works

-

1,879,522

Roads & Drainage Works for Lai King Public Housing

Estate, Stage II

582,056

Lei Muk Shue

Construction of Roads & Drainage Works

1,346,209

Lek Yuen San Tsuen, Construction of Internal Roads &

Ancillary Drainage Works

2,676,926

Road improvement for relocation of R.A.F. Facilities

from Kai Tak to Sek Kong Village

238,637

Improvement of Luk Keng Road Minimal improvements

<<

280,331

Provision of bus bay and modification of the existing road junction at Castle Peak Road junction with Tai Ho Road

197,837

Desilting Kwai Chung Main Culvert

481,502

Construction of Roads at Tai Po Lot No. 1604 and 1211

Sec. A, B, E and C Tai Po

140,000

Construction of Urn Burial Terraces

-

Wo Hop Shek

Cemetery 8th Contract

-

528,181

229