APPENDIX X - Cont'd.

(iii) New Territories

Castle Peak Road Improvement, Castle Peak to Ping Shan - Stage II

Approximate Cost

8,414,238

High Island Roads - Improved Standards

11,002,217

Man Kam To Road Bridge

1,182,279

Hang Hau Road Reconstruction

2,190,451

Construction of High Protective Fenders for the Tsing Yi Bridge

124,774

Kwai Chung Development Area 27, 28 & 29 (Part) - Drainage and roads

7,938,352

Lai Chi Kok Terrace Road

4,100,589

Lai King Low Cost Housing Estate, Stage I Roads & Drainage Works

1,879,522

Roads & Drainage Works for Lai King Public Housing Estate, Stage II

582,056

Lei Muk Shue - Construction of Roads & Drainage Works

1,346,209

Lek Yuen San Tsuen, Construction of Internal Roads & Ancillary Drainage Works

2,676,926

Road improvement for relocation of R.A.F. Facilities from Kai Tak to Sek Kong Village

238,637

Improvement of Luk Keng Road Minimal improvements

280,331

Provision of bus bay and modification of the existing road junction at Castle Peak Road junction with Tai Ho Road

197,837

Desilting Kwai Chung Main Culvert

481,502

Construction of Roads at Tai Po Lot No. 1604 and 1211 Sec. A, B, E and C Tai Po

140,000

Construction of Urn Burial Terraces - Wo Hop Shek Cemetery 8th Contract

528,181