Planning and Investigation

6.11

The feasibility reports on Yau Ma Tei typhoon shelter reclamation, development north of La Salle Road and at Tai Hom were completed. Feasibility studies on further development at Kwun Tong continued, whilst similar work at Sam Ka Tsuen was in hand. Investigation into the engineering feasibility of the development of an industrial estate north of Yuen Long was started.

6.12

The Division's annual contract for site investigation, under which works are carried out for all Offices of the Department, functioned well. The total depth of probes, drill holes, bore holes and open trial pits sunk was 14,000 metres.

Projects under Construction

6.13

Statistical details of land-formation projects under construction are given at Appendix Q and other projects at Appendices O and P.

6.14

A description of the works carried out is given below under the appropriate district headings.

Kowloon

6.15

At Lung Cheung Road Development Area 1, site formation for Section D was completed and at Ho Man Tin Development Area, road surfacing for Stage VII was also completed.

6.16

At Kowloon Bay Development Area, a contract for the construction of about 250 metres of 4-cell box culvert commenced. Reclamation continued at Kowloon Bay, where about 966,000 cubic metres of material from Government projects and private building sites was deposited to form some 19.0 hectares of land.

Kwai Chung/Tsuen Wan

6.17

The remedial works contract at Lai Chi Kok Borrow Area was completed. Reclamation at Gin Drinkers Bay was completed. Materials from Government and private works was used as covering for the tipping of refuse at Gin Drinkers Bay controlled tip.

6.18

Tuen Mun

6.19

The contract for a 1.5 Km long extension of Pillar Point Road from Pak Kok Tsui to Pillar Point was completed.

Tai Po

6.20

A site formation contract for the Tai Po Industrial Estate, Stage I commenced.

61

Edit History

2026-05-12 07:16:48 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Planning and Investigation 6.11 The feasibility reports on Yau Ma Tei typhoon shelter reclamation, development north of La Salle Road and at Tai Hom were completed. Feasibility studies on further development at Kwun Tong continued, whilst similar work at Sam Ka Tsuen was in hand. Investigation into the engineering feasibility of the development of an industrial estate north of Yuen Long was started. 6.12 The Division's annual contract for site investigation, under which works are carried out for all Offices of the Department, functioned well. The total depth of probes, drill holes, bore holes and open trial pits sunk was 14,000 metres. Projects under Construction 6.13 Statistical details of land-formation projects under construction are given at Appendix Q and other projects at Appendices O and P. 6.14 A description of the works carried out is given below under the appropriate district headings. Kowloon 6.15 At Lung Cheung Road Development Area 1, site formation for Section D was completed and at Ho Man Tin Development Area, road surfacing for Stage VII was also completed. 6.16 At Kowloon Bay Development Area, a contract for the construction of about 250 metres of 4-cell box culvert commenced. Reclamation continued at Kowloon Bay, where about 966,000 cubic metres of material from Government projects and private building sites was deposited to form some 19.0 hectares of land. Kwai Chung/Tsuen Wan 6.17 The remedial works contract at Lai Chi Kok Borrow Area was completed. Reclamation at Gin Drinkers Bay was completed. Materials from Government and private works was used as covering for the tipping of refuse at Gin Drinkers Bay controlled tip. 6.18 Tuen Mun 6.19 The contract for a 1.5 Km long extension of Pillar Point Road from Pak Kok Tsui to Pillar Point was completed. Tai Po 6.20 A site formation contract for the Tai Po Industrial Estate, Stage I commenced. 61
Baseline (Original)
Planning and Investigation 6.11 The feasibility reports on Yau Ma Tei typhoon shelter reclamation, development north of La Salle Road and at Tai Hom were completed. Feasibility studies on further development at Kwun Tong continued, whilst similar work at Sam Ka Tsuen was in hand. Investigation into the engineering feasibility of the development of an industrial estate north of Yuen Long was started. 6.12 The Division's annual contract for site investigation, under which works are carried out for all Offices of the Department, functioned well. The total depth of probes, drill holes, bore holes and open trial pits sunk was 14,000 metres. Projects under Construction 6.13 Statistical details of land-formation projects under construction are given at Appendix Q and other projects at Appendices O and P. 6.14 A description of the works carried out is given below under the appropriate district headings. Kowloon 6.15 At Lung Cheung Road Development Area 1, site formation for Section D was completed and at Ho Man Tin Development Area, road surfacing for Stage VII was also completed. 6.16 www At Kowloon Bay Development Area, a contract for the construction of about 250 metres of 4-cell box culvert commenced. Reclamation continued at Kowloon Bay, where about 966,000 cubic metres of material from Government projects and private building sites was deposited to form some 19.0 hectares of land. Kwai Chung/Tsuen Wan 6.17 The remedial works contract at Lai Chi Kok Borrow Area was completed. Reclamation at Gin Drinkers Bay was completed. Materials from Government and private works was used as covering for the tipping of refuse at Gin Drinkers Bay controlled tip. 6.18 Tuen Mun 6.19 The contract for a 1.5 Km long extension of Pillar Point Road from Pak Kok Tsui to Pillar Point was completed. Tai Po 6.20 commenced. A site formation contract for the Tai Po Industrial Estate, Stage I 61
2026-05-12 07:16:48 · Baseline
View content

Planning and Investigation

6.11

The feasibility reports on Yau Ma Tei typhoon shelter reclamation, development north of La Salle Road and at Tai Hom were completed. Feasibility studies on further development at Kwun Tong continued, whilst similar work at Sam Ka Tsuen was in hand. Investigation into the engineering feasibility of the development of an industrial estate north of Yuen Long was started.

6.12

The Division's annual contract for site investigation, under which works are carried out for all Offices of the Department, functioned well. The total depth of probes, drill holes, bore holes and open trial pits sunk was 14,000 metres.

Projects under Construction

6.13

Statistical details of land-formation projects under construction are given at Appendix Q and other projects at Appendices O and P.

6.14

A description of the works carried out is given below under the appropriate district headings.

Kowloon

6.15

At Lung Cheung Road Development Area 1, site formation for Section D was completed and at Ho Man Tin Development Area, road surfacing for Stage VII was also completed.

6.16

www

At Kowloon Bay Development Area, a contract for the construction of about 250 metres of 4-cell box culvert commenced. Reclamation continued at Kowloon Bay, where about 966,000 cubic metres of material from Government projects and private building sites was deposited to form some 19.0 hectares

of land.

Kwai Chung/Tsuen Wan

6.17

The remedial works contract at Lai Chi Kok Borrow Area was completed.

Reclamation at Gin Drinkers Bay was completed. Materials from Government and private works was used as covering for the tipping of refuse at Gin Drinkers Bay controlled tip.

6.18

Tuen Mun

6.19

The contract for a 1.5 Km long extension of Pillar Point Road from Pak Kok Tsui to Pillar Point was completed.

Tai Po

6.20

commenced.

A site formation contract for the Tai Po Industrial Estate, Stage I