main dam was well in progress. completed.

Construction of the col dams was nearly

11.119 Construction of the Eastern tunnels and intakes was substantially completed.

11.120 Civil works for the main Pumping Station was substantially completed and plant erection was in progress.

11.121

All civil engineering, mechanical and electrical contracts for the eight lowland pumping stations were awarded and construction work for the eastern group of four stations progressed satisfactorily.

Raising of Plover Cove Dams, Uprating and Extension of Sha Tin Treatment Works and Pumping Station and Tai Po Tau Pumping Station

11.122 The installation of electrical plant and services as well as instrumentation work for the scheme progressed satisfactorily.

11.123 The local/manual and automatic controls of tunnel gates were commissioned and acceptance tests carried out.

11.124 An order was placed for an extension pump for Tai Po Tau Pumping Station and manufacture of the pump was in hand.

Plover Cove Water Scheme Stages I & II

11.125 A concentrated effort was made jointly by the Waterworks Office and Legal Department in the organisation of the arbitration proceedings concerning claims on P.W.D. Contract No. 72 of 1963, Plover Cove Dam. The hearing commenced on 1st March 1976 and was continuing.

11.126

CONTRACTS & CLAIMS UNIT

Contracts & Claims Adviser:

J.B. STAUNTON, C.Eng., M.I.C.E., M.I.W.E.S.

The Unit is responsible for examining standard forms, Conditions of Contract and other standard procedures, and advises on the preparation of contract documents. In particular it aims to minimize the number and effect of claims from contractors.

11.127

Claims arising on projects managed by Waterworks Office and the Consulting Engineers were examined and liaison was maintained with the Legal Department to ensure that Government's best interests were being served.

Edit History

2026-05-12 07:40:31 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
main dam was well in progress. completed. Construction of the col dams was nearly 11.119 Construction of the Eastern tunnels and intakes was substantially completed. 11.120 Civil works for the main Pumping Station was substantially completed and plant erection was in progress. 11.121 All civil engineering, mechanical and electrical contracts for the eight lowland pumping stations were awarded and construction work for the eastern group of four stations progressed satisfactorily. Raising of Plover Cove Dams, Uprating and Extension of Sha Tin Treatment Works and Pumping Station and Tai Po Tau Pumping Station 11.122 The installation of electrical plant and services as well as instrumentation work for the scheme progressed satisfactorily. 11.123 The local/manual and automatic controls of tunnel gates were commissioned and acceptance tests carried out. 11.124 An order was placed for an extension pump for Tai Po Tau Pumping Station and manufacture of the pump was in hand. Plover Cove Water Scheme Stages I & II 11.125 A concentrated effort was made jointly by the Waterworks Office and Legal Department in the organisation of the arbitration proceedings concerning claims on P.W.D. Contract No. 72 of 1963, Plover Cove Dam. The hearing commenced on 1st March 1976 and was continuing. 11.126 CONTRACTS & CLAIMS UNIT Contracts & Claims Adviser: J.B. STAUNTON, C.Eng., M.I.C.E., M.I.W.E.S. The Unit is responsible for examining standard forms, Conditions of Contract and other standard procedures, and advises on the preparation of contract documents. In particular it aims to minimize the number and effect of claims from contractors. 11.127 Claims arising on projects managed by Waterworks Office and the Consulting Engineers were examined and liaison was maintained with the Legal Department to ensure that Government's best interests were being served.
Baseline (Original)
main dam was well in progress. completed. Construction of the col dams was nearly 11.119 Construction of the Eastern tunnels and intakes was substantially completed. 11.120 Civil works for the main Pumping Station was substantially completed and plant erection was in progress. 11.121 All civil engineering, mechanical and electrical contracts for the eight lowland pumping stations were awarded and construction work for the eastern group of four stations progressed satisfactorily. Raising of Plover Cove Dams, Uprating and Extension of Sha Tin Treatment Works and Pumping Station and Tai Po Tau Pumping Station 11.122 The installation of electrical plant and services as well as instrumentation work for the scheme progressed satisfactorily. 11.123 The local/manual and automatic controls of tunnel gates were commissioned and acceptance tests carried out. 11.124 An order was placed for an extension pump for Tai Po Tau Pumping Station and manufacture of the pump was in hand. Plover Cove Water Scheme Stages I & II 11.125 A concentrated effort was made jointly by the Waterworks Office and Legal Department in the organisation of the arbitration proceedings concerning claims on P.W.D. Contract No. 72 of 1963, Plover Cove Dam. The hearing commenced on 1st March 1976 and was continuing. 11.126 CONTRACTS & CLAIMS UNIT Contracts & Claims Adviser: J.B. STAUNTON, C.Eng., M.I.C.E., M.I.W.E.S. The Unit is responsible for examining standard forms, Conditions of Contract and other standard procedures, and advises on the preparation of contract documents. In particular it aims to minimize the number and effect of claims from contractors. 11.127 Claims arising on projects managed by Waterworks Office and the Consulting Engineers were examined and liaison was maintained with the Legal Department to ensure that Government's best interests were being served.
2026-05-12 07:40:31 · Baseline
View content

main dam was well in progress. completed.

Construction of the col dams was nearly

11.119 Construction of the Eastern tunnels and intakes was substantially completed.

11.120 Civil works for the main Pumping Station was substantially completed and plant erection was in progress.

11.121

All civil engineering, mechanical and electrical contracts for the eight lowland pumping stations were awarded and construction work for the eastern group of four stations progressed satisfactorily.

Raising of Plover Cove Dams, Uprating and Extension of Sha Tin Treatment Works and Pumping Station and Tai Po Tau Pumping Station

11.122 The installation of electrical plant and services as well as instrumentation work for the scheme progressed satisfactorily.

11.123 The local/manual and automatic controls of tunnel gates were commissioned and acceptance tests carried out.

11.124 An order was placed for an extension pump for Tai Po Tau Pumping Station and manufacture of the pump was in hand.

Plover Cove Water Scheme Stages I & II

11.125 A concentrated effort was made jointly by the Waterworks Office and Legal Department in the organisation of the arbitration proceedings concerning claims on P.W.D. Contract No. 72 of 1963, Plover Cove Dam. The hearing commenced on 1st March 1976 and was continuing.

11.126

CONTRACTS & CLAIMS UNIT

Contracts & Claims Adviser:

J.B. STAUNTON, C.Eng., M.I.C.E., M.I.W.E.S.

The Unit is responsible for examining standard forms, Conditions of Contract and other standard procedures, and advises on the preparation of contract documents. In particular it aims to minimize the number and effect of claims from contractors.

11.127

Claims arising on projects managed by Waterworks Office and the Consulting Engineers were examined and liaison was maintained with the Legal Department to ensure that Government's best interests were being served.