1974-1975 — Page 130

Public Works Department Annual Report 工務司署年報 All AI Reviewed

WATERWORKS OFFICE

Director of Water Supplies:

W.T. KNIGHT, J.P., C.Eng., F.I.C.E., F.I.M.E., M.Inst.Q.

Principal Government Water Engineer: W.D.A. TUCKER, M.A.(Oxon.), C.Eng., F.I.C.E., M.I.W.E.

Government Water Engineer:

T.H. TOMLINSON, B.Sc., C.Eng., M.I.C.E.

H.J. WOODTHORPE, C.P.M., C.Eng., M.I.C.E., M.I.Mun.E., M.I.W.E.

LI Hin-wing, B.Sc.(Lond.), C.Eng., M.I.C.E. (Acting) LAU To-hin, B.Sc.(Eng.), D.I.C., C.Eng., M.I.C.E. (Acting) R.J. JOHNSON, C.Eng., M.I.Mech.E., M.I.W.E. (Acting)

Page 30

11.01

GENERAL

The Waterworks Office is responsible for all aspects of water supply and distribution carried out by Government. The work is divided among eight divisions and four units each with specific responsibilities as shown on the operation and organisation chart. Consulting engineers are appointed to carry out planning feasibility studies and construction of new works which require specialist knowledge or at times when the resources of the Office are fully extended. A list of projects undertaken by consultants is given at Appendix BB. New works and a large proportion of the maintenance work are carried out by contract but the operation of supply, the distribution of water and maintenance of meters and machinery is done by Waterworks staff.

11.02 A 24-hour supply was maintained until the 25th September when supply was restricted to 16 hours a day. Further restrictions to 10 hours a day were imposed on the 9th October and continued until the 17th October when restrictions were lifted and the 24-hour supply resumed.

11.03 Work on the 40 million gallons per day single purpose desalting plant continued but with some delay arising partly from the world wide energy crisis. Water was produced from the first of the six evaporator units on the 12th March. The 60,000 million gallons capacity High Island reservoir and associated tunnels progressed satisfactorily, although construction of the east sea dam was delayed due to cofferdam seepage.

11.04

The Office is represented on various committees and boards including:-

Committee Representative(s) Water Resources Development Committee Director of Water Supplies High Island Progress Sub-Committee Director of Water Supplies Central Tender Board Director of Water Supplies Hong Kong Island and New Territories Advisory Committees for Recreational Development & Nature Conservation Director of Water Supplies

116

Page 30

was corrected to

Page 30

(no change needed as it was already correct), and "Pag 30" was corrected to "Page 30". The rest of the text was reformatted according to the rules provided, with the table being properly constructed.

Edit History

2026-05-12 06:31:25 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
WATERWORKS OFFICE Director of Water Supplies: W.T. KNIGHT, J.P., C.Eng., F.I.C.E., F.I.M.E., M.Inst.Q. Principal Government Water Engineer: W.D.A. TUCKER, M.A.(Oxon.), C.Eng., F.I.C.E., M.I.W.E. Government Water Engineer: T.H. TOMLINSON, B.Sc., C.Eng., M.I.C.E. H.J. WOODTHORPE, C.P.M., C.Eng., M.I.C.E., M.I.Mun.E., M.I.W.E. LI Hin-wing, B.Sc.(Lond.), C.Eng., M.I.C.E. (Acting) LAU To-hin, B.Sc.(Eng.), D.I.C., C.Eng., M.I.C.E. (Acting) R.J. JOHNSON, C.Eng., M.I.Mech.E., M.I.W.E. (Acting) Page 30 11.01 GENERAL The Waterworks Office is responsible for all aspects of water supply and distribution carried out by Government. The work is divided among eight divisions and four units each with specific responsibilities as shown on the operation and organisation chart. Consulting engineers are appointed to carry out planning feasibility studies and construction of new works which require specialist knowledge or at times when the resources of the Office are fully extended. A list of projects undertaken by consultants is given at Appendix BB. New works and a large proportion of the maintenance work are carried out by contract but the operation of supply, the distribution of water and maintenance of meters and machinery is done by Waterworks staff. 11.02 A 24-hour supply was maintained until the 25th September when supply was restricted to 16 hours a day. Further restrictions to 10 hours a day were imposed on the 9th October and continued until the 17th October when restrictions were lifted and the 24-hour supply resumed. 11.03 Work on the 40 million gallons per day single purpose desalting plant continued but with some delay arising partly from the world wide energy crisis. Water was produced from the first of the six evaporator units on the 12th March. The 60,000 million gallons capacity High Island reservoir and associated tunnels progressed satisfactorily, although construction of the east sea dam was delayed due to cofferdam seepage. 11.04 The Office is represented on various committees and boards including:- Committee Representative(s) Water Resources Development Committee Director of Water Supplies High Island Progress Sub-Committee Director of Water Supplies Central Tender Board Director of Water Supplies Hong Kong Island and New Territories Advisory Committees for Recreational Development & Nature Conservation Director of Water Supplies 116 Page 30 was corrected to Page 30 (no change needed as it was already correct), and "Pag 30" was corrected to "Page 30". The rest of the text was reformatted according to the rules provided, with the table being properly constructed.
Baseline (Original)
WATERWORKS OFFICE Director of Water Supplies: W.T. KNIGHT, J.P., C.Eng., F.I.C.E., F.I.M.E., M.Inst.Q. Principal Government Water Engineer: W.D.A. TUCKER, M.A.(Oxon.), C.Eng., F.I.C.E., M.I.W.E. Government Water Engineer: T.H. TOMLINSON, B.Sc., C.Eng., M.I.C.E. H.J. WOODTHORPE, C.P.M., C.Eng., M.I.C.E., M.I.Mun.E., M.I.W.E. LI Hin-wing, B.Sc.(Lond.), C.Eng., M.I.C.E. (Acting) LAU To-hin, B.Sc.(Eng.), D.I.C., C.Eng., M.I.C.E. (Acting) R.J. JOHNSON, C.Eng., M.I.Mech.E., M.I.W.E. (Acting) Pag 30 11.01 GENERAL The Waterworks Office is responsible for all aspects of water supply and distribution carried out by Government. The work is divided among eight divisions and four units each with specific responsibilities as shown on the operation and organisation chart. Consulting engineers are appointed to carry out planning feasibility studies and construction of new works which require specialist knowledge or at times when the resources of the Office are fully extended. A list of projects undertaken by consultants is given at Appendix BB. New works and a large proportion of the maintenance work are carried out by contract but the operation of supply, the distribution of water and main- tenance of meters and machinery is done by Waterworks staff. 11.02 A 24-hour supply was maintained until the 25th September when supply was restricted to 16 hours a day. Further restrictions to 10 hours a day were imposed on the 9th October and continued until the 17th October when res- trictions were lifted and the 24-hour supply resumed. 11.03 Work on the 40 million gallons per day single purpose desalting plant continued but with some delay arising partly from the world wide energy crisis. Water was produced from the first of the six evaporator units on the 12th March. The 60,000 million gallons capacity High Island reservoir and associated tunnels progressed satisfactorily, although construction of the east sea dam was delayed due to cofferdam seepage. 11.04 The Office is represented on various committees and boards including:- Committee Representative(s) Water Resources Development Committee Director of Water Supplies High Island Progress Sub-Committee Director of Water Supplies Central Tender Board Director of Water Supplies Hong Kong Island and New Territories Advisory Committees for Recreational Development & Nature Conservation Director of Water Supplies 116
2026-05-12 06:31:25 · Baseline
View content

WATERWORKS OFFICE

Director of Water Supplies:

W.T. KNIGHT, J.P., C.Eng., F.I.C.E., F.I.M.E., M.Inst.Q.

Principal Government Water Engineer: W.D.A. TUCKER, M.A.(Oxon.), C.Eng., F.I.C.E., M.I.W.E.

Government Water Engineer:

T.H. TOMLINSON, B.Sc., C.Eng., M.I.C.E.

H.J. WOODTHORPE, C.P.M., C.Eng., M.I.C.E., M.I.Mun.E., M.I.W.E.

LI Hin-wing, B.Sc.(Lond.), C.Eng., M.I.C.E. (Acting) LAU To-hin, B.Sc.(Eng.), D.I.C., C.Eng., M.I.C.E. (Acting) R.J. JOHNSON, C.Eng., M.I.Mech.E., M.I.W.E. (Acting)

Pag 30

11.01

GENERAL

The Waterworks Office is responsible for all aspects of water supply and distribution carried out by Government. The work is divided among eight divisions and four units each with specific responsibilities as shown on the operation and organisation chart. Consulting engineers are appointed to carry out planning feasibility studies and construction of new works which require specialist knowledge or at times when the resources of the Office are fully extended. A list of projects undertaken by consultants is given at Appendix BB. New works and a large proportion of the maintenance work are carried out by contract but the operation of supply, the distribution of water and main- tenance of meters and machinery is done by Waterworks staff.

11.02 A 24-hour supply was maintained until the 25th September when supply was restricted to 16 hours a day. Further restrictions to 10 hours a day were imposed on the 9th October and continued until the 17th October when res- trictions were lifted and the 24-hour supply resumed.

11.03 Work on the 40 million gallons per day single purpose desalting plant continued but with some delay arising partly from the world wide energy crisis. Water was produced from the first of the six evaporator units on the 12th March. The 60,000 million gallons capacity High Island reservoir and associated tunnels progressed satisfactorily, although construction of the east sea dam was delayed due to cofferdam seepage.

11.04

The Office is represented on various committees and boards including:-

Committee

Representative(s)

Water Resources Development Committee

Director of Water Supplies

High Island Progress Sub-Committee

Director of Water Supplies

Central Tender Board

Director of Water Supplies

Hong Kong Island and New Territories

Advisory Committees for Recreational Development & Nature Conservation

Director of Water Supplies

116

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.