1967-1968 — Page 68

Public Works Department Annual Report 工務司署年報 All AI Reviewed

Kwun Tong Public Pier

5.41. A reinforced concrete roof has been constructed over this pier for the benefit of the public.

Shuen Wan Typhoon Shelter

5.42. The armouring of the breakwater arm for the Shuen Wan Typhoon Shelter, Tolo Harbour, continued and about 60% was completed. This breakwater will provide 27 acres of typhoon shelter for local craft.

Ferry Piers at Tsuen Wan and North Tsing Yi

5.43. Two piers are under construction at Yau Kom Tau and at North Tsing Yi for use by a minor ferry service which will provide a link between the mainland and North Tsing Yi.

Tathong Point Landing

5.44. Tenders were called for the construction of a landing at Tathong Point, which is the southern tip of Tung Lung Island. This landing will facilitate access to the navigational aids situated on the island and will enable men and equipment to be landed in most types of weather.

Refuse Disposal Incinerators

5.45. Progress on the plant installation is described in paras. 7.17 & 7.18 of the Electrical and Mechanical Office section. The design of the civil engineering and building works at both Kennedy Town and Lai Chi Kok was carried out by a firm of consultants while the contract management of the civil works was the responsibility of this Division. At Lai Chi Kok, where the incinerator building and civil engineering work has been substantially completed, construction of a refuse collection pier and a salt water pumphouse to serve the incinerators was started. The internal roads are being surfaced so that the first incinerator may operate pending a decision on the second which is planned for construction within the same compound.

Maintenance and Dredging

5.46. General maintenance and repairs were carried out to a number of government piers, seawalls, breakwaters, markers and light beacons.

48

Edit History

2026-05-12 00:35:39 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Kwun Tong Public Pier 5.41. A reinforced concrete roof has been constructed over this pier for the benefit of the public. Shuen Wan Typhoon Shelter 5.42. The armouring of the breakwater arm for the Shuen Wan Typhoon Shelter, Tolo Harbour, continued and about 60% was completed. This breakwater will provide 27 acres of typhoon shelter for local craft. Ferry Piers at Tsuen Wan and North Tsing Yi 5.43. Two piers are under construction at Yau Kom Tau and at North Tsing Yi for use by a minor ferry service which will provide a link between the mainland and North Tsing Yi. Tathong Point Landing 5.44. Tenders were called for the construction of a landing at Tathong Point, which is the southern tip of Tung Lung Island. This landing will facilitate access to the navigational aids situated on the island and will enable men and equipment to be landed in most types of weather. Refuse Disposal Incinerators 5.45. Progress on the plant installation is described in paras. 7.17 & 7.18 of the Electrical and Mechanical Office section. The design of the civil engineering and building works at both Kennedy Town and Lai Chi Kok was carried out by a firm of consultants while the contract management of the civil works was the responsibility of this Division. At Lai Chi Kok, where the incinerator building and civil engineering work has been substantially completed, construction of a refuse collection pier and a salt water pumphouse to serve the incinerators was started. The internal roads are being surfaced so that the first incinerator may operate pending a decision on the second which is planned for construction within the same compound. Maintenance and Dredging 5.46. General maintenance and repairs were carried out to a number of government piers, seawalls, breakwaters, markers and light beacons. 48
Baseline (Original)
Kwun Tong Public Pier 5.41. A reinforced concrete roof has been constructed over this pier for the benefit of the public. Shuen Wan Typhoon Shelter 5.42. The armouring of the breakwater arm for the Shuen Wan Typhoon Shelter, Tolo Harbour, continued and about 60% was completed. This breakwater will provide 27 acres of typhoon shelter for local craft. Ferry Piers at Tsuen Wan and North Tsing Yi 5.43. Two piers are under construction at Yau Kom Tau and at North Tsing Yi for use by a minor ferry service which will provide a link between the mainland and North Tsing Yi. Tathong Point Landing 5.44. Tenders were called for the construction of a landing at Tathong Point, which is the southern tip of Tung Lung Island. This landing will facilitate access to the navigational aids situated on the island and will enable men and equipment to be landed in most types of weather. Refuse Disposal Incinerators 5.45. Progress on the plant installation is described in paras. 7.17 & 7.18 of the Electrical and Mechanical Office section. The design of the civil engineering and building works at both Kennedy Town and Lai Chi Kok was carried out by a firm of consultants while the contract management of the civil works was the responsibility of this Division. At Lai Chi Kok, where the incinerator building and civil engineering work has been substantially completed, construction of a refuse collec- tion pier and a salt water pumphouse to serve the incinerators was started. The internal roads are being surfaced so that the first incinerator may operate pending a decision on the second which is planned for construction within the same compound. Maintenance and Dredging 5.46. General maintenance and repairs were carried out to a number of government piers, seawalls, breakwaters, markers and light beacons. 48
2026-05-12 00:35:39 · Baseline
View content

Kwun Tong Public Pier

5.41. A reinforced concrete roof has been constructed over this pier for the benefit of the public.

Shuen Wan Typhoon Shelter

5.42. The armouring of the breakwater arm for the Shuen Wan Typhoon Shelter, Tolo Harbour, continued and about 60% was completed. This breakwater will provide 27 acres of typhoon shelter for local craft.

Ferry Piers at Tsuen Wan and North Tsing Yi

5.43. Two piers are under construction at Yau Kom Tau and at North Tsing Yi for use by a minor ferry service which will provide a link between the mainland and North Tsing Yi.

Tathong Point Landing

5.44. Tenders were called for the construction of a landing at Tathong Point, which is the southern tip of Tung Lung Island. This landing will facilitate access to the navigational aids situated on the island and will enable men and equipment to be landed in most types of weather.

Refuse Disposal Incinerators

5.45. Progress on the plant installation is described in paras. 7.17 & 7.18 of the Electrical and Mechanical Office section. The design of the civil engineering and building works at both Kennedy Town and Lai Chi Kok was carried out by a firm of consultants while the contract management of the civil works was the responsibility of this Division. At Lai Chi Kok, where the incinerator building and civil engineering work has been substantially completed, construction of a refuse collec- tion pier and a salt water pumphouse to serve the incinerators was started. The internal roads are being surfaced so that the first incinerator may operate pending a decision on the second which is planned for construction within the same compound.

Maintenance and Dredging

5.46. General maintenance and repairs were carried out to a number of government piers, seawalls, breakwaters, markers and light beacons.