1964-1965 — Page 49

Public Works Department Annual Report 工務司署年報 All AI Reviewed

Location

Kwun Tong New Town...

Area to be formed (acres) Estimated Cost ($M) Area Expenditure completed ($M) (acres) to 31.3.64 670.48 105.00 593.40 Sam Ka Tsuen 40.00 12.60 3.00 Kowloon Bay 426.00 94.20 53.10 Nil Ho Man Tin Development... 121.00 22.70 34.50 Lung Cheung Road Development Area No. 3 47.00 7.50 47.00 Remarks 70.30 Additional area at Sau Mau Ping resulting from revised layout. 2.01 Site formation commenced in February 1965. Reclamation formed by public dumping. 5.23 Site for residential and community use. Road works in progress on stages II and III and in road No. 6A linking Nairn Road with Ma Tau Wei Road. 3.25 Sites for residential and community use completed. Internal road works under construction. Kwai Chung North Development Area 9... 90.00 22.00 30.00 4.10 Sites for resettlement, low cost housing and workers' housing. 1,394.48 264.00 761.00 84.89

Kwun Tong

4.10. Of the six site formation contracts in progress two were completed during the year. A total of 51.4 acres of levelled building sites was formed in the New Town and 13.3 acres of reclamation completed in Industrial Zone 5.

4.11. Reclamation continued in an adjacent section of Kowloon Bay and some 1,115,000 cubic yards of material from private building sites and Government projects was deposited to form 34.47 acres of land. The total area reclaimed in Kowloon Bay including Kai Tak was 53.10 acres.

4.12. Work commenced in February 1965 on the development of a 40 acre site at Sam Ka Tsuen to the South East of Kwun Tong to provide land for heavy industry.

Page 32

Edit History

2026-05-11 23:11:04 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Location Kwun Tong New Town... Area to be formed (acres) Estimated Cost ($M) Area Expenditure completed ($M) (acres) to 31.3.64 670.48 105.00 593.40 Sam Ka Tsuen 40.00 12.60 3.00 Kowloon Bay 426.00 94.20 53.10 Nil Ho Man Tin Development... 121.00 22.70 34.50 Lung Cheung Road Development Area No. 3 47.00 7.50 47.00 Remarks 70.30 Additional area at Sau Mau Ping resulting from revised layout. 2.01 Site formation commenced in February 1965. Reclamation formed by public dumping. 5.23 Site for residential and community use. Road works in progress on stages II and III and in road No. 6A linking Nairn Road with Ma Tau Wei Road. 3.25 Sites for residential and community use completed. Internal road works under construction. Kwai Chung North Development Area 9... 90.00 22.00 30.00 4.10 Sites for resettlement, low cost housing and workers' housing. 1,394.48 264.00 761.00 84.89 Kwun Tong 4.10. Of the six site formation contracts in progress two were completed during the year. A total of 51.4 acres of levelled building sites was formed in the New Town and 13.3 acres of reclamation completed in Industrial Zone 5. 4.11. Reclamation continued in an adjacent section of Kowloon Bay and some 1,115,000 cubic yards of material from private building sites and Government projects was deposited to form 34.47 acres of land. The total area reclaimed in Kowloon Bay including Kai Tak was 53.10 acres. 4.12. Work commenced in February 1965 on the development of a 40 acre site at Sam Ka Tsuen to the South East of Kwun Tong to provide land for heavy industry. Page 32
Baseline (Original)
Location Kwun Tong New Town... Area to be formed (acres) Estimated Cost ($M) Area Expenditure completed ($M) (acres) to 31.3.64 670.48 105,00 593.40 Sam Ka Tsuen 40.00 12.60 3.00 ... Kowloon Bay 426.00 94.20 53.10 Nil Ho Man Tin Development... 121.00 22.70 34.50 Lung Cheung Road Develop- ment Area No. 3 47.00 7.50 47.00 Remarks 70.30 Additional area at Sau Mau Ping resulting from revised layout. 2.01 Site formation commen- ced in February 1965. Reclamation formed by public dumping. 5.23 Site for residential and community use. Road works in progress on stages II and III and in road No. 6A linking Nairn Road with Ma Tau Wei Road. 3.25 Sites for residential and community use com- pleted. Internal road works under construc- tion. Kwai Chung North Develop- ment Area 9 ... 90.00 22.00 30.00 4.10 Sites for resettlement, low cost housing and workers' housing. 1,394.48 264.00 761.00 84.89 Kwun Tong 4.10. Of the six site formation contracts in progress two were com- pleted during the year. A total of 51.4 acres of levelled building sites was formed in the New Town and 13.3 acres of reclamation completed in Industrial Zone 5. 4.11. Reclamation continued in an adjacent section of Kowloon Bay and some 1,115,000 cubic yards of material from private building sites and Government projects was deposited to form 34.47 acres of land. The total area reclaimed in Kowloon Bay including Kai Tak was 53.10 acres. 4.12. Work commenced in February 1965 on the development of a 40 acre site at Sam Ka Tsuen to the South East of Kwun Tong to provide land for heavy industry. 32
2026-05-11 23:11:04 · Baseline
View content

Location

Kwun Tong New

Town...

Area to be formed

(acres)

Estimated Cost ($M)

Area Expenditure completed ($M)

(acres) to 31.3.64

670.48

105,00

593.40

Sam Ka Tsuen

40.00

12.60

3.00

...

Kowloon Bay

426.00

94.20

53.10

Nil

Ho Man Tin

Development...

121.00

22.70

34.50

Lung Cheung

Road Develop-

ment Area

No. 3

47.00

7.50

47.00

Remarks

70.30 Additional area at Sau Mau Ping resulting from revised layout.

2.01 Site formation commen-

ced in February 1965.

Reclamation formed by public dumping.

5.23 Site for residential and community use. Road works in progress on stages II and III and in road No. 6A linking Nairn Road with Ma Tau Wei Road.

3.25 Sites for residential and community use com- pleted. Internal road works under construc- tion.

Kwai Chung

North Develop-

ment Area 9 ... 90.00 22.00

30.00

4.10 Sites for resettlement, low cost housing and workers' housing.

1,394.48 264.00 761.00

84.89

Kwun Tong

4.10. Of the six site formation contracts in progress two were com- pleted during the year. A total of 51.4 acres of levelled building sites was formed in the New Town and 13.3 acres of reclamation completed in Industrial Zone 5.

4.11. Reclamation continued in an adjacent section of Kowloon Bay and some 1,115,000 cubic yards of material from private building sites and Government projects was deposited to form 34.47 acres of land. The total area reclaimed in Kowloon Bay including Kai Tak was 53.10 acres.

4.12. Work commenced in February 1965 on the development of a 40 acre site at Sam Ka Tsuen to the South East of Kwun Tong to provide land for heavy industry.

32

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.