Area to be formed (acres) Estimated Cost ($M) Area Expenditure completed ($M) (acres) to 31.3.64 670.48 105.00 593.40 Sam Ka Tsuen 40.00 12.60 3.00 Kowloon Bay 426.00 94.20 53.10 Nil Ho Man Tin Development... 121.00 22.70 34.50 Lung Cheung Road Development Area No. 3 47.00 7.50 47.00 Remarks 70.30 Additional area at Sau Mau Ping resulting from revised layout. 2.01 Site formation commenced in February 1965. Reclamation formed by public dumping. 5.23 Site for residential and community use. Road works in progress on stages II and III and in road No. 6A linking Nairn Road with Ma Tau Wei Road. 3.25 Sites for residential and community use completed. Internal road works under construction. Kwai Chung North Development Area 9... 90.00 22.00 30.00 4.10 Sites for resettlement, low cost housing and workers' housing. 1,394.48 264.00 761.00 84.89Kwun Tong
4.10. Of the six site formation contracts in progress two were completed during the year. A total of 51.4 acres of levelled building sites was formed in the New Town and 13.3 acres of reclamation completed in Industrial Zone 5.
4.11. Reclamation continued in an adjacent section of Kowloon Bay and some 1,115,000 cubic yards of material from private building sites and Government projects was deposited to form 34.47 acres of land. The total area reclaimed in Kowloon Bay including Kai Tak was 53.10 acres.
4.12. Work commenced in February 1965 on the development of a 40 acre site at Sam Ka Tsuen to the South East of Kwun Tong to provide land for heavy industry.
Page 32