Additional Salt-Water Flushing Supplies at Aberdeen

10.43. A start was made on the laying of 5000′ of 10″ and 15″ diameter asbestos-cement pipes. Quotations for the supply of pumping equipment were invited.

Pok Fu Lam Water Supply Stage 1-Queen Mary Hospital

10.44. Realignment of Victoria Road to make room for the new Telegraph Bay Pumping Station was completed and design of the pumping station and plant layout was commenced.

Pok Fu Lam Water Supply Stage II

10.45. Survey and site investigations for the 2-million-gallon Kai Lung Wan Service Reservoir were completed and design begun.

Chai Wan Distribution System

10.46. Mainlaying proceeded in conjunction with the formation of new roads.

Enlargement of Distribution Mains in Stubbs Road Area

10.47. Mainlaying was begun in Stubbs Road between Shiu Fai Terrace and Tung Shan Terrace.

Choi Hung Estate Water Supply

10.48. Fresh- and salt-water mains continued to be laid as required by development.

Kwun Tong New Town Water Supply

10.49. Fresh- and salt-water mains continued to be laid in the housing zones, commercial centre and industrial zones as required by development and in conjunction with road works.

Kwun Tong High-Level Supply

10.50. Construction work on the 6 m.g. fresh- and the 0.5 m.g. salt-water service reservoirs proceeded and excavation of the sites were almost completed together with about 80% of the main mass-concrete walls. Concreting of column footings and invert slab was started. The design of the Shum Wan Shan Pumping Station was commenced and quotations for supply of pumping equipment were invited.

Water Supply to Tsz Wan Shan and Wang Tau Hom Resettlement Estates

10.51. Laying of the inlet and outlet mains for the previously constructed fresh- and salt-water service reservoirs was delayed because

78

Edit History

2026-05-11 22:52:59 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Additional Salt-Water Flushing Supplies at Aberdeen 10.43. A start was made on the laying of 5000′ of 10″ and 15″ diameter asbestos-cement pipes. Quotations for the supply of pumping equipment were invited. Pok Fu Lam Water Supply Stage 1-Queen Mary Hospital 10.44. Realignment of Victoria Road to make room for the new Telegraph Bay Pumping Station was completed and design of the pumping station and plant layout was commenced. Pok Fu Lam Water Supply Stage II 10.45. Survey and site investigations for the 2-million-gallon Kai Lung Wan Service Reservoir were completed and design begun. Chai Wan Distribution System 10.46. Mainlaying proceeded in conjunction with the formation of new roads. Enlargement of Distribution Mains in Stubbs Road Area 10.47. Mainlaying was begun in Stubbs Road between Shiu Fai Terrace and Tung Shan Terrace. Choi Hung Estate Water Supply 10.48. Fresh- and salt-water mains continued to be laid as required by development. Kwun Tong New Town Water Supply 10.49. Fresh- and salt-water mains continued to be laid in the housing zones, commercial centre and industrial zones as required by development and in conjunction with road works. Kwun Tong High-Level Supply 10.50. Construction work on the 6 m.g. fresh- and the 0.5 m.g. salt-water service reservoirs proceeded and excavation of the sites were almost completed together with about 80% of the main mass-concrete walls. Concreting of column footings and invert slab was started. The design of the Shum Wan Shan Pumping Station was commenced and quotations for supply of pumping equipment were invited. Water Supply to Tsz Wan Shan and Wang Tau Hom Resettlement Estates 10.51. Laying of the inlet and outlet mains for the previously constructed fresh- and salt-water service reservoirs was delayed because 78
Baseline (Original)
Additional Salt-Water Flushing Supplies at Aberdeen 10.43. A start was made on the laying of 5000′ of 10′′ and 15′′ diameter asbestos-cement pipes. Quotations for the supply of pumping equipment were invited. Pok Fu Lam Water Supply Stage 1-Queen Mary Hospital 10.44. Realignment of Victoria Road to make room for the new Telegraph Bay Pumping Station was completed and design of the pumping station and plant layout was commenced. Pok Fu Lam Water Supply Stage II 10.45. Survey and site investigations for the 2-million-gallon Kai Lung Wan Service Reservoir were completed and design begun. Chai Wan Distribution System 10.46. Mainlaying proceeded in conjunction with the formation of new roads. Enlargement of Distribution Mains in Stubbs Road Area 10.47. Mainlaying was begun in Stubbs Road between Shiu Fai Terrace and Tung Shan Terrace. Choi Hung Estate Water Supply 10.48. Fresh- and salt-water mains continued to be laid as required by development. Kwun Tong New Town Water Supply 10.49. Fresh- and salt-water mains continued to be laid in the housing zones, commercial centre and industrial zones as required by development and in conjunction with road works. Kwun Tong High-Level Supply 10.50. Construction work on the 6 m.g. fresh- and the 0.5 m.g. salt-water service reservoirs proceeded and excavation of the sites were almost completed together with about 80% of the main mass-concrete walls. Concreting of column footings and invert slab was started. The design of the Shum Wan Shan Pumping Station was commenced and quotations for supply of pumping equipment were invited. Water Supply to Tsz Wan Shan and Wang Tau Hom Resettlement Estates 10.51. Laying of the inlet and outlet mains for the previously con- structed fresh- and salt-water service reservoirs was delayed because 78
2026-05-11 22:52:59 · Baseline
View content

Additional Salt-Water Flushing Supplies at Aberdeen

10.43. A start was made on the laying of 5000′ of 10′′ and 15′′ diameter asbestos-cement pipes. Quotations for the supply of pumping equipment were invited.

Pok Fu Lam Water Supply Stage 1-Queen Mary Hospital

10.44. Realignment of Victoria Road to make room for the new Telegraph Bay Pumping Station was completed and design of the pumping station and plant layout was commenced.

Pok Fu Lam Water Supply Stage II

10.45. Survey and site investigations for the 2-million-gallon Kai Lung Wan Service Reservoir were completed and design begun.

Chai Wan Distribution System

10.46. Mainlaying proceeded in conjunction with the formation of new roads.

Enlargement of Distribution Mains in Stubbs Road Area

10.47. Mainlaying was begun in Stubbs Road between Shiu Fai Terrace and Tung Shan Terrace.

Choi Hung Estate Water Supply

10.48. Fresh- and salt-water mains continued to be laid as required by development.

Kwun Tong New Town Water Supply

10.49. Fresh- and salt-water mains continued to be laid in the housing zones, commercial centre and industrial zones as required by development and in conjunction with road works.

Kwun Tong High-Level Supply

10.50. Construction work on the 6 m.g. fresh- and the 0.5 m.g. salt-water service reservoirs proceeded and excavation of the sites were almost completed together with about 80% of the main mass-concrete walls. Concreting of column footings and invert slab was started. The design of the Shum Wan Shan Pumping Station was commenced and quotations for supply of pumping equipment were invited.

Water Supply to Tsz Wan Shan and Wang Tau Hom Resettlement

Estates

10.51. Laying of the inlet and outlet mains for the previously con- structed fresh- and salt-water service reservoirs was delayed because