1959-1960 — Page 20

Public Works Department Annual Report 工務司署年報 All AI Reviewed

59. A total of 32 domestic blocks were completed. An average of one block every 11 days might at first give the impression that the various projects were completed without any great difficulty.

60. In fact during the year, the architects, engineers and contractors responsible for the Resettlement programme faced and overcame several problems. Many resulted from the exceptional rains of June at Kwun Tong – some 60,000 cubic yards of filling were washed away and the site took weeks to dry out sufficiently for work to proceed. Piling in boulder-strewn ground also caused difficulty on many sites, and foundation designs had to be varied to suit the circumstances. This occurred particularly at Chai Wan where one block is constructed partly on bedrock, partly on piles and partly on a raft; and at Kwun Tong where the presence of boulders made piling impractical and necessitated deep excavation for foundations.

Shek Kip Mei (Stage IV)

61. Two domestic blocks and the hawker market were completed early in March 1960.

Lo Fu Ngam (Stage I)

62. The last two blocks of this contract are approaching completion.

Lo Fu Ngam (Stage II)

63. The four blocks in this stage were completed in March 1960.

Wong Tai Sin (Areas A & B)

64. Phase III (a). The six blocks in this phase were completed in November 1959.

65. Phase III (b). The two blocks in this phase were completed in March 1960.

Jordan Valley

66. The flatted factory and eight of the nine domestic blocks in the section south of the main nullah were completed. Two of the blocks contained about 200 self-contained flats.

67. Site formation and piling work on the section north of the main nullah are now complete and construction of the domestic block has started.

12

Page

Edit History

2026-05-11 20:50:21 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
59. A total of 32 domestic blocks were completed. An average of one block every 11 days might at first give the impression that the various projects were completed without any great difficulty. 60. In fact during the year, the architects, engineers and contractors responsible for the Resettlement programme faced and overcame several problems. Many resulted from the exceptional rains of June at Kwun Tong some 60,000 cubic yards of filling were washed away and the site took weeks to dry out sufficiently for work to proceed. Piling in boulder-strewn ground also caused difficulty on many sites, and foundation designs had to be varied to suit the circumstances. This occurred particularly at Chai Wan where one block is constructed partly on bedrock, partly on piles and partly on a raft; and at Kwun Tong where the presence of boulders made piling impractical and necessitated deep excavation for foundations. Shek Kip Mei (Stage IV) 61. Two domestic blocks and the hawker market were completed early in March 1960. Lo Fu Ngam (Stage I) 62. The last two blocks of this contract are approaching completion. Lo Fu Ngam (Stage II) 63. The four blocks in this stage were completed in March 1960. Wong Tai Sin (Areas A & B) 64. Phase III (a). The six blocks in this phase were completed in November 1959. 65. Phase III (b). The two blocks in this phase were completed in March 1960. Jordan Valley 66. The flatted factory and eight of the nine domestic blocks in the section south of the main nullah were completed. Two of the blocks contained about 200 self-contained flats. 67. Site formation and piling work on the section north of the main nullah are now complete and construction of the domestic block has started. 12 Page
Baseline (Original)
59. A total of 32 domestic blocks were completed. An average of one block every 11 days might at first give the impression that the various projects were completed without any great difficulty. 60. In fact during the year, the architects, engineers and contractors responsible for the Resettlement programme faced and overcame several problems. Many resulted from the exceptional rains of June at Kwun Tong some 60,000 cubic yards of filling were washed away and the site took weeks to dry out sufficiently for work to proceed. Piling in boulder strewn ground also caused difficulty on many sites, and foun- dation designs had to be varied to suit the circumstances. This occurred particularly at Chai Wan where one block is constructed partly on bed rock, partly on piles and partly on a raft; and at Kwun Tong where the presence of boulders made piling impractical and necessitated deep excavation for foundations. Shek Kip Mei (Stage IV) 61. Two domestic blocks and the hawker market were completed early in March 1960. Lo Fu Ngam (Stage 1) 62. The last two blocks of this contract are approaching completion. Lo Fu Ngam (Stage II) 63. The four blocks in this stage were completed in March 1960. Wong Tai Sin (Areas A & B) 64. Phase III (a). The six blocks in this phase were completed in November 1959. 65. Phase III (b). The two blocks in this phase were completed in March 1960. Jordan Valley 66. The flatted factory and eight of the nine domestic blocks in the section south of the main nullah were completed. Two of the blocks contained about 200 self-contained flats. 67. Site formation and piling work on the section north of the main nullah are now complete and construction of the domestic block has started. 12 Page
2026-05-11 20:50:21 · Baseline
View content

59. A total of 32 domestic blocks were completed. An average of one block every 11 days might at first give the impression that the various projects were completed without any great difficulty.

60. In fact during the year, the architects, engineers and contractors responsible for the Resettlement programme faced and overcame several problems. Many resulted from the exceptional rains of June at Kwun Tong some 60,000 cubic yards of filling were washed away and the site took weeks to dry out sufficiently for work to proceed. Piling in boulder strewn ground also caused difficulty on many sites, and foun- dation designs had to be varied to suit the circumstances. This occurred particularly at Chai Wan where one block is constructed partly on bed rock, partly on piles and partly on a raft; and at Kwun Tong where the presence of boulders made piling impractical and necessitated deep excavation for foundations.

Shek Kip Mei (Stage IV)

61. Two domestic blocks and the hawker market were completed early in March 1960.

Lo Fu Ngam (Stage 1)

62. The last two blocks of this contract are approaching completion.

Lo Fu Ngam (Stage II)

63. The four blocks in this stage were completed in March 1960.

Wong Tai Sin (Areas A & B)

64. Phase III (a). The six blocks in this phase were completed in November 1959.

65. Phase III (b). The two blocks in this phase were completed in March 1960.

Jordan Valley

66. The flatted factory and eight of the nine domestic blocks in the section south of the main nullah were completed. Two of the blocks contained about 200 self-contained flats.

67. Site formation and piling work on the section north of the main nullah are now complete and construction of the domestic block has started.

12

Page

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.