86. Cadastral Survey of New Territories. In order to enable a complete new cadastral survey of the New Territories to be undertaken, camps for survey parties are required in various parts of the New Territories.

87. The first one to be erected was at Tsun Wan and consists of:

(a) Living accommodation for Assistant Surveyors and Survey coolies.

(b) Drawing Office, office for Surveyor-in-charge and store. (c) Two garages.

88. The buildings are of pre-fabricated timber units, which can on completion of the survey in that area be dismantled and re-erected elsewhere.

89. Construction of the Tsun Wan camp was started in January.

90. New Offices, etc. Kowloon. Preliminary sketch plans were commenced for new Departmental Offices, Workshops and Depots in Kowloon. The proposed site for this development is at the corner of Ma Tau Wei Road and Farm Road.

Resettlement Department

91. Shek Kip Mei Resettlement Flats. A brief reference was made in last year's report under the heading of "Rehousing of Shek Kip Mei Fire Victims" to the preparation of plans for six-storey reinforced concrete buildings.

92. These blocks have been designed with back-to-back rooms, each set of rooms having external balcony approach and communal lavatory facilities. Through ventilation to the rooms has been provided by "honeycomb" building in the top four courses of brickwork of the dividing cross partition. Each


15

Edit History

2026-05-11 20:02:05 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
86. Cadastral Survey of New Territories. In order to enable a complete new cadastral survey of the New Territories to be undertaken, camps for survey parties are required in various parts of the New Territories. 87. The first one to be erected was at Tsun Wan and consists of: (a) Living accommodation for Assistant Surveyors and Survey coolies. (b) Drawing Office, office for Surveyor-in-charge and store. (c) Two garages. 88. The buildings are of pre-fabricated timber units, which can on completion of the survey in that area be dismantled and re-erected elsewhere. 89. Construction of the Tsun Wan camp was started in January. 90. New Offices, etc. Kowloon. Preliminary sketch plans were commenced for new Departmental Offices, Workshops and Depots in Kowloon. The proposed site for this development is at the corner of Ma Tau Wei Road and Farm Road. Resettlement Department 91. Shek Kip Mei Resettlement Flats. A brief reference was made in last year's report under the heading of "Rehousing of Shek Kip Mei Fire Victims" to the preparation of plans for six-storey reinforced concrete buildings. 92. These blocks have been designed with back-to-back rooms, each set of rooms having external balcony approach and communal lavatory facilities. Through ventilation to the rooms has been provided by "honeycomb" building in the top four courses of brickwork of the dividing cross partition. Each 15
Baseline (Original)
86. Cadastral Survey of New Territories. In order to enable a complete new cadastral survey of the New Territories to be undertaken, camps for survey parties are required in various parts of the New Territories. 87. The first one to be erected was at Tsun Wan and consists of: (a) Living accommodation for Assistant Surveyors and Survey coolies. (b) Drawing Office, office for Surveyor-in-charge and store. (c) Two garages. 88. The buildings are of pre-fabricated timber units, which can on completion of the survey in that area be dismantled and re-erected elsewhere. 89. Construction of the Tsun Wan camp was started in January. 90. New Offices, etc. Kowloon. Preliminary sketch plans were commenced for new Departmental Offices, Workshops and Depots in Kowloon. The proposed site for this development is at the corner of Ma Tau Wei Road and Farm Road. Resettlement Department 91. Shek Kip Mei Resettlement Flats. A brief reference was made in last year's report under the heading of "Rehousing of Shek Kip Mei Fire Victims" to the preparation of plans for six-storey reinforced concrete buildings. 92. These blocks have been designed with back-to-back rooms, each set of rooms having external balcony approach and communal lavatory facilities. Through ventilation to the rooms has been provided by "honeycomb" building in the top four courses of brickwork of the dividing cross partition. Each 15
2026-05-11 20:02:05 · Baseline
View content

86. Cadastral Survey of New Territories. In order to enable a complete new cadastral survey of the New Territories to be undertaken, camps for survey parties are required in various parts of the New Territories.

87. The first one to be erected was at Tsun Wan and consists of:

(a) Living accommodation for Assistant Surveyors and

Survey coolies.

(b) Drawing Office, office for Surveyor-in-charge and store. (c) Two garages.

88. The buildings are of pre-fabricated timber units, which can on completion of the survey in that area be dismantled and re-erected elsewhere.

89. Construction of the Tsun Wan camp was started in January.

90. New Offices, etc. Kowloon. Preliminary sketch plans were commenced for new Departmental Offices, Workshops and Depots in Kowloon. The proposed site for this development is at the corner of Ma Tau Wei Road and Farm Road.

Resettlement Department

91. Shek Kip Mei Resettlement Flats. A brief reference was made in last year's report under the heading of "Rehousing of Shek Kip Mei Fire Victims" to the preparation of plans for six-storey reinforced concrete buildings.

92. These blocks have been designed with back-to-back rooms, each set of rooms having external balcony approach and communal lavatory facilities. Through ventilation to the rooms has been provided by "honeycomb" building in the top four courses of brickwork of the dividing cross partition. Each

15

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.