79. The work was completed in July.

80. Stanley Prison-Assembly & Dining Hall. This is an open sided structure, with a steel truss roof covered with asbestos sheeting, covering an area 123 feet by 61 feet.

One end of the building has a built-up stage with a dressing room adjoining, so that in addition to dining, the hall may be used as an assembly or concert hall.

81. Building work was commenced in February.

Training Centre.

82. Quarters for Stanley

Working drawings were completed for a pair of semi-detached houses for the officers-in-charge, a block of four flats for schoolmasters, and a block of sixteen flats and five single rooms for Leaders and Instructors.

Public Works Department

83. New Electrical & Mechanical Workshops.

Details of this scheme were given in last year's report. Building work on the Mechanical Workshops, which are 400 feet long and 132 feet wide, commenced in September.

84. Since the new building is within the same area as the existing workshops, which have had to be kept in operation during the process of re-building, the new construction has been planned to be erected in three sections; each section to be completed and handed over ready for operation before the next section can be commenced. This process has considerably lengthened the time required for completion of the work, but by the end of March the first section had been completed and good progress had been made on the second section.

85. Preliminary sketch plans for the Electrical Workshop, Stores and Offices were also completed.

14

Page 27

Edit History

2026-05-11 20:02:00 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
79. The work was completed in July. 80. Stanley Prison-Assembly & Dining Hall. This is an open sided structure, with a steel truss roof covered with asbestos sheeting, covering an area 123 feet by 61 feet. One end of the building has a built-up stage with a dressing room adjoining, so that in addition to dining, the hall may be used as an assembly or concert hall. 81. Building work was commenced in February. Training Centre. 82. Quarters for Stanley Working drawings were completed for a pair of semi-detached houses for the officers-in-charge, a block of four flats for schoolmasters, and a block of sixteen flats and five single rooms for Leaders and Instructors. Public Works Department 83. New Electrical & Mechanical Workshops. Details of this scheme were given in last year's report. Building work on the Mechanical Workshops, which are 400 feet long and 132 feet wide, commenced in September. 84. Since the new building is within the same area as the existing workshops, which have had to be kept in operation during the process of re-building, the new construction has been planned to be erected in three sections; each section to be completed and handed over ready for operation before the next section can be commenced. This process has considerably lengthened the time required for completion of the work, but by the end of March the first section had been completed and good progress had been made on the second section. 85. Preliminary sketch plans for the Electrical Workshop, Stores and Offices were also completed. 14 Page 27
Baseline (Original)
79. The work was completed in July. 80. Stanley Prison-Assembly & Dining Hall. This is an open sided structure, with a steel truss roof covered with asbestos sheeting, covering an area 123 feet by 61 feet. One end of the building has a built-up stage with a dressing room adjoining, so that in addition to dining, the hall may be used as an assembly or concert hall. 81. Building work was commenced in February. · Training Centre. 82. Quarters for Stanley Working drawings were completed for a pair of semi-detached houses for the officers-in-charge, a block of four flats for schoolmasters, and a block of sixteen flats and five single rooms for Leaders and Instructors. Pubic Works Department 83. New Electrical & Mechanical Workshops. Details of this scheme were given in last year's report. Building work on the Mechanical Workshops, which are 400 feet long and 132 feet wide, commenced in September. 84. Since the new building is within the same area as the existing workshops, which have had to be kept in operation during the process of re-building, the new construction has been planned to be erected in three sections; each section to be com- pleted and handed over ready for operation before the next section can be commenced. This process has considerably lengthened the time required for completion of the work, but by the end of March the first section had been completed and good progress had been made on the second section. 85. Preliminary sketch plans for the Electrical Workshop, Stores and Offices were also completed. 14 Pag Jake 27
2026-05-11 20:02:00 · Baseline
View content

79. The work was completed in July.

80. Stanley Prison-Assembly & Dining Hall. This is an open sided structure, with a steel truss roof covered with asbestos sheeting, covering an area 123 feet by 61 feet.

One end of the building has a built-up stage with a dressing room adjoining, so that in addition to dining, the hall may be used as an assembly or concert hall.

81. Building work was commenced in February.

·

Training Centre.

82. Quarters for Stanley

Working drawings were completed for a pair of semi-detached houses for the officers-in-charge, a block of four flats for schoolmasters, and a block of sixteen flats and five single rooms for Leaders and Instructors.

Pubic Works Department

83. New Electrical & Mechanical Workshops.

Details of this scheme were given in last year's report. Building work on the Mechanical Workshops, which are 400 feet long and 132 feet wide, commenced in September.

84. Since the new building is within the same area as the existing workshops, which have had to be kept in operation during the process of re-building, the new construction has been planned to be erected in three sections; each section to be com- pleted and handed over ready for operation before the next section can be commenced. This process has considerably lengthened the time required for completion of the work, but by the end of March the first section had been completed and good progress had been made on the second section.

85. Preliminary sketch plans for the Electrical Workshop, Stores and Offices were also completed.