A 10 CAP. 400J
Noise Control (General) Regulations
[1989 Ed.
[Subsidiary]
FORM 2
NOISE CONTROL ORDINANCE
(Chapter 400) Section 8(2)
APPLICATION FOR A CONSTRUCTION NOISE PERMIT FOR THE CARRYING OUT OF PERCUSSIVE PILING
Before completing this form read the Note below
To: The Noise Control Authority
1.
2.
3.
4.
I
[reg. 4]
hereby apply under section 8(2) of the Noise Control Ordinance for a construction noise permit for the carrying out of percussive piling.
In support of my application I submit the following information and particulars:
Details of Applicant
2a. Name (person or company):...
2b. H.K. Identity Card No. (if the applicant is an individual):...
or Business Registration No. (if the applicant is a company):...
2c. Correspondence address:
2d. Telephone No.:
Construction site where the percussive piling is to be carried out
3a. Full street address:
Lot No.:
3b. A plan of suitable scale preferably 1:1000 showing-
(i) either the piling zone, that is, the area within which percussive piling is to take place
or the actual pile locations; and
(ii) the noise sensitive receivers in the area surrounding the site including domestic premises, hotels, hostels, temporary housing accommodation, hospitals, medical clinics, educational institutions, places of public worship, libraries, courts of law, performing arts centres or office buildings but excluding industrial premises.
3c. If the applicant wishes the Authority to consider applying the correction for the effect of any barrier, additional cross-sectional drawings showing any substantial barrier should be submitted.
Detailed information regarding the application
4a. Details of any previous application for the carrying out of percussive piling in relation to the same site:
Indicate by ticking in the appropriate box whether:
No previous application has been made.
If previous application has been made, indicate whether:
The application was refused.
OR
A permit was issued.
Construction noise permit No.:
Date of expiry:
4b. Duration for which the construction noise permit is required:
Duration:
Dates: From
To
(Specify days/weeks/months) (inclusive)
Page 10
Page 11
A 10 CAP. 400J
Noise Control (General) Regulations
[1989 Ed.
[Subsidiary]
FORM 2
NOISE CONTROL ORDINANCE
(Chapter 400) Section 8(2)
APPLICATION FOR A CONSTRUCTION NOISE PERMIT FOR THE CARRYING OUT OF PERCUSSIVE PILING
Before completing this form read the Note below
To: The Noise Control Authority
1.
2.
3.
4.
I
[reg. 4]
hereby apply under section 8(2) of the Noise Control
Ordinance for a construction noise permit for the carrying out of percussive piling.
In support of my application I submit the following information and particulars:
Details of Applicant
2a. Name (person or company):...
26. H.K. Identity Card No. (if the applicant is an individual):..
or Business Registration No. (if the applicant is a company):.
2c. Correspondence address:
2d. Telephone No.:
Construction site where the percussive piling is to be carried out 3a. Full street address:
Lot No.:
3b. A plan of suitable scale preferably 1:1 000 showing-
(i) either the piling zone, that is, the area within which percussive piling is to take place
or the actual pile locations; and
(ii) the noise sensitive receivers in the area surrounding the site including domestic premises, hotels, hostels, temporary housing accommodation, hospitals, medical clinics, educational institutions, places of public worship, libraries, courts of law, performing arts centres or office buildings but excluding industrial premises.
3c. If the applicant wishes the Authority to consider applying the correction for the effect of any barrier, additional cross-sectional drawings showing any substantial barrier should be submitted.
Detailed information regarding the application
4a. Details of any previous application for the carrying out of percussive piling in relation to
the same site:
Indicate by ticking in the appropriate box whether:
No previous application has been made.
If previous application has been made, indicate whether:
The application was refused.
OR
A permit was issued.
Construction noise permit No.:
Date of expiry:
4b. Duration for which the construction noise permit is required:
Duration:
Dates: From
To
(Specify days/weeks/months) (inclusive)
Page 10Page 11