TNAG-2661-FCO40-3857-Future-of-Hong-Kong-British-Consulate-General-1992 — Page 101

FCO40 Hong Kong Department Records 聯邦事務部香港部檔案 All

>

The offices are wrongly split in half by the waiting area D10.

9.

Level 6

(a)

(b)

(c)

The Exhibition areas (J6) should not be in two halves.

Chamber of Commerce suite (D20) should be before the waiting/reception: a separate entrance from the lift lobby would be ideal.

Location of Conference room (J5) via Registry is incorrect. The Registry should not be a corridor

(d)

of eren a

corridor?

[scenario].

(e)

The B/R security arrangements are no longer required. However access control by (D9) from the waiting area (D10) to the staff offices is still necessary.

10.

(£)

Room J7 is missing.

(g)

Access to D14 is not as per the brief.

(h)

Commercial Section should be moved to the next level · see para 2 (b) above.

Level 7

(a) F6 appears on the large side.

Consideration to be given to locating J8 in a less prestigious area than E Section.

Relationship between J1 and F13 is not ideal.

(b)

(c)

(d)

The Sections on this floor should be located on the 8th floor - see para 2 (b) above.

PCAS3.148