List of Contracts for new Airport and related Projects
Brief Scope of Contract
6. Airport Site Preparation Contract
(Contract No. PAA 1/91)- excavation of approximately 90 million cu.m of Chek Lap Kok Island and formation of a site of 1250ha for the airport, including construction of seawall & drainage work.
7.
Airport People Mover System (Contract No. 350)
Prequalification and Tender Invitation
Date
Notice of Prequalification published on 15.3.91 Tenders invited on 18 November 1991
(returned on
12 March 1992)
Revised Tenders invited
on 8 May 1992
(returned on
26 June 1992)
Contractor selected on
31 July 1992.
Prequalification was invited on 13 August 1992. Tenders to be invited in Nov/Dec 1992.
as at 1 Septem
992
Commencement/ Completion
Dates
Contractor/
Managing Department/ Officer In-charge
Contract Sum $M (MOD)
Origin
Funding Source/ PWP No.
Sept/Oct 1992
to
Provisional Airport Authority |(Mr F Uiterwijk - 824 7333)
$9,041M
PAA
December 1994
June 1993
Provisional Airport Authority To be determined (Mr David Corby - 824 7337)
PAA
18.
Aircraft Maintenance and Aircargo Handling Facilities
9. Aviation Fuel Storage/Distribution
(Contract No. 840)
Prequalification
submissions were
received in August 1992. Tenders to be invited in Oct/Nov 1992.
Prequalification will be invited in September 1992.
Tenders to be invited lin December 1992
mid 1993
Provisional Airport Authority |(Mr David Corby - 824 7337)
To be determined
PAA
Provisional Airport Authority |(Mr David Corby - 824 7337)
To be determined
PAA