List of Contracts for new Airport and related Projects

Brief Scope of Contract

6. Airport Site Preparation Contract

(Contract No. PAA 1/91)- excavation of approximately 90 million cu.m of Chek Lap Kok Island and formation of a site of 1250ha for the airport, including construction of seawall & drainage work.

7.

Airport People Mover System (Contract No. 350)

Prequalification and Tender Invitation

Date

Notice of Prequalification published on 15.3.91 Tenders invited on 18 November 1991

(returned on

12 March 1992)

Revised Tenders invited

on 8 May 1992

(returned on

26 June 1992)

Contractor selected on

31 July 1992.

Prequalification was invited on 13 August 1992. Tenders to be invited in Nov/Dec 1992.

as at 1 Septem

992

Commencement/ Completion

Dates

Contractor/

Managing Department/ Officer In-charge

Contract Sum $M (MOD)

Origin

Funding Source/ PWP No.

Sept/Oct 1992

to

Provisional Airport Authority |(Mr F Uiterwijk - 824 7333)

$9,041M

PAA

December 1994

June 1993

Provisional Airport Authority To be determined (Mr David Corby - 824 7337)

PAA

18.

Aircraft Maintenance and Aircargo Handling Facilities

9. Aviation Fuel Storage/Distribution

(Contract No. 840)

Prequalification

submissions were

received in August 1992. Tenders to be invited in Oct/Nov 1992.

Prequalification will be invited in September 1992.

Tenders to be invited lin December 1992

mid 1993

Provisional Airport Authority |(Mr David Corby - 824 7337)

To be determined

PAA

Provisional Airport Authority |(Mr David Corby - 824 7337)

To be determined