New Airport Capital Costs

following is

a

comparison

Annex A

between the capital

costs at March 1991 prices now estimated for the project and as

they were last estimated in July 1991 -

Total Construction Cost for AA (Site Preparation, Airfield, passenger terminal etc)

July 1991 Estimates

$28,300m

Current Cost Estimates

$30,500m

AA Management/Operating Costs etc during construction

$ 3,200m

$ 3,200m

Total AA Capital Cost

$31,500m

$33,700m

Estimated Cost of Government Facilities

$ 3,100m

$ 3,100m

Estimated Cost of Tenant Support Facilities

$10,200m

$ 9,500m

Total Airport Capital Cost

$44,800m

$46,300m