The
New Airport Capital Costs
following is
a
comparison
Annex A
between the capital
costs at March 1991 prices now estimated for the project and as
they were last estimated in July 1991 -
Total Construction Cost for AA (Site Preparation, Airfield, passenger terminal etc)
July 1991 Estimates
$28,300m
Current Cost Estimates
$30,500m
AA Management/Operating Costs etc during construction
$ 3,200m
$ 3,200m
Total AA Capital Cost
$31,500m
$33,700m
Estimated Cost of Government Facilities
$ 3,100m
$ 3,100m
Estimated Cost of Tenant Support Facilities
$10,200m
$ 9,500m
Total Airport Capital Cost
$44,800m
$46,300m