M (90) 41
CONFIDENTIAL
374
two projects; and
(c)
in view of the importance of ensuring
that the two bridges are completed and
schedule, the need to make provision
on
in
the contract(s) for the payment of
damages and/or performance
liquidated
bonds
in the
event of failure to
complete the work or to complete the
work on schedule, should be closely
examined.
IN ATTENDANCE
Mr C.F. MAK
Deputy Secretary (Transport)
Mr S.K. KWEI - Director of Highways
Miss D. YUE
Principal Assistant Financial Secretary
A560
RENEGOTIATION OF A NEW FRANCHISE FOR PASSENGER BAGGAGE AND CARGO HANDLING
AT HONG KONG INTERNATIONAL AIRPORT: XCC (90)163
DECISION
that
The Council ADVISED and the Governor ORDERED
a new exclusive
franchise for the
remaining life of Kai Tak should be
negotiated with Hong Kong Air Terminal
Services Limited on the basis set out in
CONFIDENTIAL
No comments yet.