NEW AIRPORT AND RELATED PROJECTS
LIST OF CONTRACTS ENVISAGED TO BE INVITED FOR TENDER
IN NEXT TWELVE MONTES
8 October 1990
ril
gineering
Brief Scope of Contracti
1. Airport Advance Works - reciamation of
+
15ha, including construction of a 650m long seawall, in the bay area of northern Chek Lap Kok to provide a site to house workers'
accommodation and other facilities as preparatory works for the airport construction.
2. West Kowloon Reclamation - Northern Arca
Phase I (Contract No. UA5/90) - reclamation
of about 38ha and construciton of 1700m of
scatvall adjacent to Tai Kok Tsui/Sham Shui Po to provide land for the West Kowloon Expressway, the airport railway and other developments as well as construction of replacement ferry piers and marino facilities including market and cargo-handling piers.
"
13. Construction of Yau Ma Tei Replacement
Typhoon Shelter Phase II and Jordan Road Reclamation Phase I (Contract No. CV/90/09) - construction of about 4,000m of vertical sca wall/revetament, reclamation of about 69ha of land and reprovisioning of a public cargo working area. The reclaimed land is to provide the landfall for the Western Harbour Crossing, other airport related transport infrastructures and other urban development.
4. Lantau Fixed Crossing - constructing of a Tkm long crossing between Tsing Yi Island and Lantau Island, in the form of suspension bridges or tunnels. The crossing will carry a dual-three-lane road a twin-track railway.
Expected Tender Invitation Dato
Notices of Prequalification gazetied on 24.8.90. Tenders to be invited from prequalified tenderers in November 1990.
Notices of Prequalification gazetted on 5.10.90. Tenders to be invited from prequalified toaderers in December 1990.
Notices of Prequalification gazetted on 10.8.90. Tenders to be invited from prequalified {tenderers in December 1990.
February 1991 (Prequalification of (tenders to be carried out in
November 1990.)
5. Airport Main Site Formation and Reclamation - September 1991 (may be advanced
excavation of approx. 90 million cu m of Chek Lato March 1991) (Prequalification of Kok Island and reclamation of about 1,000 ha forteadorers to be carried out prior to the new airport site, including construction of seawalls and drainage works.
tendering)
Magazine Dopertinent!
Officer In-charge
Civil Engineering Servicos Department (Mr M S Leung - (368 9768)
Territory Development Department
(Mr K Austin - 848 2668)
Civil Engineering Services Department (Mr M S Leung- 368 9768)
Highways Department (Mr KS Leung → 721 6540)
Civil Engineering Services Department
[(Mr M 5 Leung - 368 9768)