HOPEWELL HOLDINGS LIMITED BOT (BUILD
-
OPERATE - TRANSFER)
TRANSFER) PROJECTS
NAME
COUNTRY
NATURE
SIZE
HK$M
COMPL.
Remarks
1
China Resources Building
HONG KONG
2
China Hotel,
CHINA
52 storey Office Block
Hotel Office
145000 sq.m.
425 M
July 83 25 months from Caisson to
Occupation Permit.
Guangzhou
3
Broadwood Road
HONG KONG
2 Lane Road
1200 rooms 168000 sq.m.
1200 m
800 M
Dec. 83 Soft Opening in 28 months.
88 M
4
Cross Border
CHINA
Station,
Immigration Custom
60100 sq.m.
160 M
Apr. 84 Surrender to HK Government after
completion. June 85 Re-purchased by China Government
Shenzhen
Complex
5
Shajiao B Power Station
CHINA
Coal-fired
2x350 MW
4,368 M
July 87 Completed
4/87
6
Navotas Gas-Turbine
MANILA
Power Station
Power Station
200 MW
320 M
Oct. 90 Synchronized
8/90
Power Station
7
Guangzhou-Zhuhai-
CHINA
Superhighway
120.2 KM
9,800 M
Shenzhen
Superhighway
network, Stage 1
Sept. 93 Border Station
completed
12/89
***
8
Shajiao C Power Station
CHINA
Coal-fired Power Station
2x660 MW
7,800 M
Dec. 93 State Council
approval
5/90
9
San Juan Power Station
PHILIPPINES
Coal-fired Power Station
2x350 MW
5,460 M
June 94 Tender accepted
6/90
10
Bangkok Elevated & Road Train System
THAILAND
(BERTS), BANGKOK
Mass Transit System & Property Development
60.1 KM
25,000 M
Oct. 98 Thai Cabinet approval First Freeway First Trains
5/90
4/93
10/94
Synchronization was achieved in month 22 after start of site work, 11 month ahead of a 33 month programme, a world record. The Shajiao Group of engineers, contractors were award the British Construction Industrial Awards 1988 on Civil Engieering.
Size possession given December 1989. Piling commenced January 1990. In the 9 months there were three typhoons, one coup and one earthquake.
Last stretch of right of way acquired on March 1990, after 6 years of negotiations. Bank syndication of US$800M will be underwritened September 1990.
TABLE NO.
2