I
+
levels of traffic noise and air pollution and the
loss of sea views. Property depreciation would
provide grounds for strong objections from the
affected land owners and would therefore
introduce further delays.
ii.
The proposed channel between the Port Island and
N. Lantau might provide access in the harbour.
This concept should be further considered in the
development of the Port Peninsula element of PADS
Projects.
b.
PADS Projects
i. The West Kowloon Reclamation has been gazetted
and most of the objections received are related
to the details of the reprovisioning of maritime
and water-related industries. There were no
objections from the general public with regard to
the impact on the environment.
17.
Flexibility and Robustness
a.
Mr. Gordon Wu's Proposal
i.
It prematurely commits all of the port facilities
in the Western Harbour as part of the initial
construction, and thus leaves little room for