AIRPORT
1.
2.
3.
4.
PORT & AIRPORT DEVELOPMENT STRATEGY (PADS)
SALIENT POINTS
Kai Tak will reach capacity by 1996.
Economic disbenefit 1996 - 2010 if new airport is not built
HK$101 billion (US$12.9 billion).
New airport at Chek Lap Kok -
(a) 1000 ha site;
(b)
Two runways capacity of 70-74 'planes/hr;
(c)
Potential long term capacity of airport passengers p.a. and 4.4 million tonnes of cargo;
80 million
(a)
First runway to be commissioned by January 1997;
(e)
Total cost of airport at 1990 prices HK$38 billion
(US$5 billion) (£3 billion);
ww
(f)
(g)
(h)
(1)
Provisional Airport Authority has been enacted;
consultants for Airport Master Layout Plan to be appointed shortly;
Management consultants to oversee airport and airport related projects; to be appointed shortly;
Advance airport site preparation work to start in early 1991; and
(j) Main works to start in 1992.
Associated with the new airport will be a support community of 150,000 at Tung Chung. A further township for 110,000 at Tai Ho.
@