Airport Railway : MTRC has been invited to build
and operate. Engineering feasibility study to start early
1990 to be followed by financial study.
8.
North Lantau Expressway
dual 3-lane. Design
review to update work done in 1982 is in hand.
Costs and Funding
9.
At 1989 prices and to cope
cope with
with demand up to
2006, cost is estimated at HK$127 billion (port $50
billion, airport $35 billion, transport $27 billion, Lantau development and utilities $15 billion). Expenditure to be
spread over a number of years. Benefits from releasing
land on
on which Kai Tak stands and relaxation of development
restrictions on rest of Kowloon need also to be borne in
mind. Between 40% and 60% of costs could be met by private
sector.
Inflationary Impact
10.
PADS, taken with other major private and public
sector developments, will put heavy pressure on
construction industry. Will lead to upward pressure on
construction costs, labour costs and, in due course, this
may spread to other sectors. Careful phasing will help minimize these pressures. Selective importation of labour may be necessary in peak years of activity.
Why Chek Lap Kok Strategy?
11.
Chosen from over 40 potential strategies because
(a) Cheaper (by 20%) and quicker to build than main
alternative site in Western Harbour;