CONFIDENTIAL
185.
НКС 062 li
442735
MDHIAN 4443
CONFIDENTIAL
FM HONG KONG
TO IMMEDIATE FCO
TELNO 2476
OF 24120OZ JULY 89
INFO PRIORITY PEKING, UKREP JLG HONG KONG
PERSONAL FOR PAUL HKD FROM GOVERNOR
MY 4TH IPT: CENTRAL
-
WANCHAI RECLAMATION TIMETABLE
THE TIMETABLE WE ARE NOW WORKING TO ON THE CENTRAL-WANCHI RECLAMAT-
ION PROJECT IS AS FOLLOWS:
(A) END AUGUST 1989:
FINAL REPORT SUBMITTED BY CONSULTANTS. (THIS IS PUBLIC KNOWLEDGE AND WE HAVE NO MORE REASONABLE EXCUSES FOR DELAY).
(B) 22 SEPTEMBER 1989:
REPORT SUBMITTED TO LAND DEVELOPMENT POLICY COMMITTEE FOR ENDORSEMENT. (THIS IS A GOVERNMENT BODY: NO STATEMENT NEED BE MADE).
(C) LATE SEPTEMBER/OCTOBER 1989:
SUBMISSION TO PUBLIC WORKS VETTING COMMITTEE TO CREATE A PROJECT ITEM IN CATEGORY C (I.E. PLANNED BUT NO COMMITMENT OF FUNDS). ALSO, PREPARATION OF REVISED OUTLINE ZONING PLAN COZP) FOR CENTRAL AND
WANCHAI
(D) END OCTOBER 1989:
SUBMISSION TO PUBLIC WORKS SUB-COMMITTEE OF FINANCE COMMITTEE UPGRADE ADVANCE WORKS AND RECLAMATION WORKS TO CATEGORY AB SO THAT CONSULTANTS FOR DETAILED DESIGN AND SITE INVESTIGATION CAN BE
APPOINTED.
TO
(E) NOVEMBER/DECEMBER 1989:
SUBMISSION OF REVISED OZP TO TOWN PLANNING BOARD AND GAZETTE. TWO
MONTHS ALLOWED FOR OBJECTIONS.