FM HONG KONG

TO IMMEDIATE FCO

TELNO 2476

OF 24120OZ JULY 89

INFO PRIORITY PEKING, UKREP JLG HONG KONG

PERSONAL FOR PAUL HKD FROM GOVERNOR

MY 4TH IPT: CENTRAL

-

WANCHAI RECLAMATION TIMETABLE

THE TIMETABLE WE ARE NOW WORKING TO ON THE CENTRAL-WANCHI RECLAMAT-

ION PROJECT IS AS FOLLOWS:

(A) END AUGUST 1989:

FINAL REPORT SUBMITTED BY CONSULTANTS. (THIS IS PUBLIC KNOWLEDGE AND WE HAVE NO MORE REASONABLE EXCUSES FOR DELAY).

(B) 22 SEPTEMBER 1989:

REPORT SUBMITTED TO LAND DEVELOPMENT POLICY COMMITTEE FOR ENDORSEMENT. (THIS IS A GOVERNMENT BODY: NO STATEMENT NEED BE MADE).

(C) LATE SEPTEMBER/OCTOBER 1989:

SUBMISSION TO PUBLIC WORKS VETTING COMMITTEE TO CREATE A PROJECT ITEM IN CATEGORY C (I.E. PLANNED BUT NO COMMITMENT OF FUNDS). ALSO, PREPARATION OF REVISED OUTLINE ZONING PLAN COZP) FOR CENTRAL AND

WANCHAI

(D) END OCTOBER 1989:

SUBMISSION TO PUBLIC WORKS SUB-COMMITTEE OF FINANCE COMMITTEE UPGRADE ADVANCE WORKS AND RECLAMATION WORKS TO CATEGORY AB SO THAT CONSULTANTS FOR DETAILED DESIGN AND SITE INVESTIGATION CAN BE

APPOINTED.

TO

(E) NOVEMBER/DECEMBER 1989:

SUBMISSION OF REVISED OZP TO TOWN PLANNING BOARD AND GAZETTE. TWO

MONTHS ALLOWED FOR OBJECTIONS.