9

-

9.50 am

PMS

MR POON:

Mr Chairman, following on that, you did

say that even if he sought guidance, it would not be proper for you to give him guidance because it is within their purview to get the job done properly. Now for normal building of domestic flats or factories one would have accepted that. May I be enlightened as to this particular job, whether there are special features which a normal contractor would rely on the expertise of the consultants to give him guidance when he finds that certain parts of the work that he has done does not produce the desired result, for instance stopping water from leakage. And the second part of

G

-

my question is that if it is found that the work was deficient, would it have been the proper procedure I don't know because I am a layman that you would report that this particular firm was not performing their duties to get it right and perhaps the contract would be stopped and given to another one.

MR MOTTRAM:

No, I think it all gets back to the point

I made before that bad concrete work essentially is not discovered until such time as the form-work or the shuttering protecting or

encasing the concrete is removed. At that time it would become immediately evident to the Clerk of Works as it would to the

structural engineer that there was honeycombing in the concrete.

At that stage we then instructed the contractor to take certain

remedial measures at that particular time. As I recall, we even instructed him to demolish one of the walls and rebuild it again,

it was so bad. The decision was made in consultation with the

Architectural Office that a certain approach would be made to the

rectification of that concrete and this was agreed in meetings with

the Architectural Office, the liaison engineers, liaison and the consulting engineers.

CHAIRMAN:

MR CHAN:

architects,

Any further questions?

Was the high water table at the location

of the basement expected before the design work commenced?