NEW TERRITORIES CIRCULAR ROAD IMPROVEMENTS

AU TAU TO FAN KAM ROAD PHASE 3 FAIRVIEW PARK TO MAI PO (PART)

SECTIONS FROM POK WAI TO SHEUNG SAN WAI AND FROM

YAU MEI SAN TSUEN TO WAI TSAI

Objections received

+

SERIAL NUMBER & DATE

14

21.12.1986

NAME OF OBJECTOR

BRIEF

DESCRIPTION

OF OBJECTION

HyD's

INTERPRETATION

OF VALIDITY

HyD's COMMENTS

AND WHETHER

SCHEME SHOULD

BE AMENDED

CLARIFICATION FROM OBJECTORS REQUIRED

WHETHER LEGAL

ADVICE

Mr MAN Kam-hing

The objector considered that Government's proposed resumption of the major portion of his lot would leave the remaining small portion hardly usable. He therefore requested Government for total resumption of his lot.

The objector's request is in fact covered under Section 23 of the Roads (Works, Use and Compensation) Ordinance.

As DLO/YL has advised that it is Government's current policy that resumption of land should be the minimum necessary to implement the project, no modification is possible.

Although the objector had been explained that he could apply, under Section 23 of the Roads Ordinance, for resumption of any contiguous or adjacent land and that withdrawal of the objection would not prejudice his rights under Section 23, the objector refused to withdraw his objection.

Νο

REQUIRED

WHETHER CONSULT-

ATION WITH OTHER

No

DEPARTMENTS

REQUIRED

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.