method, and detailed costing of the various

elements. The costs would however be subject to

continuous refinement in the following months.

Mid/Late

A summary of the resource based cost estimates will

September be available.

1st

October

Report on the Final Cost Estimates for the Civil

Engineering works. Although it is recognised that

there might be some slippage, it is agreed that this

date should be the final date at which the Financial

Consultants would accept revisions to civil

engineering cost estimates.

23