TNAG-1175-FCO40-1477-Proposed-replacement-airport-for-Hong-Kong-at-Deep-Bay-or-Ch-1982 — Page 135

FCO40 Hong Kong Department Records 聯邦事務部香港部檔案 All

ATTACHMENT D

SUMMARY OF COST INFORMATION AVAILABLE TO FINANCIAL CONSULTANTS

1982

(a)

April

Order of magnitude construction costs for civil

works. Figures may be a best estimate or presented

as a range. They will be based on subjective

judgement and experience of similar type projects.

The costs will be split down into categories.

preliminary list of these "Elements in the Cost

Summary" was made available to the Financial

Consultants.

A

Only the Civil Engineering Design

elements on the Summary list would be costed at this

stage.

(b)

May

(c)

1st June

Cost estimates provided in April should be regarded

as preliminary estimates only, subject to revision.

The remaining elements on the summary list, relating

to Master Plan studies, will be costed, and the

results made available to the Financial Consultants.

These will probably not need subsequent revision.

The design for the civil engineering works will be

frozen and a refinement of the preliminary costs

provided in April might then be possible, but this

would still not be a detailed resource based

estimate.

(a)

August

Work would be undertaken on producing resource based

final cost estimates. This would involve selection

of a scheme of work to implement the chosen design

22