Task 2.

Review of cost data

2.1

This task will be undertaken concurrently with the revenue

analysis as cost estimates become available. Early review

of cost classifications with the master plan consultant

and civil engineering consultant will ensure consistency

of cost data for engineering and financial purposes.

major costs are:

Two

(1)

capital outlays and

(2) operating and maintenance expenses

Cost data will be recorded on a periodic basis consistent

with the revenue projections so that a direct comparison

can be made over the "base case period" and the cost and

revenue projections so recorded will provide the basis for

an overall financial assessment of the project.

2.2

The cost estimates provided by the master plan consultant

vill be compared, for consistency, with Kai Tak's

historical costs and trends and also against available

cost data for other recently constructed airports.

Inflation factors will be cross-checked against projected

appropriate price indices. Any questions or apparent

inconsistencies will be discussed with Government and

Master Plan consultant SO as to achieve a "best set" of

cost estimates.