TNAG-1139-FCO40-1419-Quarterly-progress-reports-on-Hong-Kong-1982 — Page 54

FCO40 Hong Kong Department Records 聯邦事務部香港部檔案 All

機密

CONFIDENTIAL

LANDS AND WORKS BRANCH QUARTERLY PROGRESS REPORT

1st May 1982 to 31st July 1982

Subject

Purpose

3. Major Development

Studies

(a) North Lantau

(LW(SPU)70/61/10)

To make a conprehensive study of the development potential of various sub- regions in Hong Kong to provide the basic infor- mation on a comparable basis for the selection of a preferred develop- ment strategy.

Progress Made & Present Position

The special team established to guide the development of the land use/ transportation optimization (LUTO) model continued with its work as programmed.

Next Quarter Targets

LUTO team to complete its work on model development by September 1982, and to seek consultancy assistance for data production relating to Junk Bay, Ma On Shan and possibly, North Lantau.

(a) North Lantau

(i) The development of con-

ceptual planning pro- posals and detailed engineering studies have reached a concluding stage, ready for submis- sion as an interim report. (ii) Replacement airport at Chek Lap Kok: detailed civil engineering,

environmental, financial, meteorological and master plan studies are proceeding.

(iii) Consultancy studies on the

detailed design of the Lantau Fixed Crossing continuing.

(a) North Lantau

(i) LDPC to con-

sider interim report.

CONFIDENTIAL

To strengthen the existing ik house working team for furth detailed studi leading to the final report.

(ii) Monitor progress

in consultancy studies related to CLK replace- ment airport.

(iii) Monitor progress

in detailed

design of the Lantau Fixed

Crossing.

GE 323

2.

Comments