CONSTRUCTION COSTS
The Consultants have developed cost estimates for constructing the replacement airport based on prices prevailing as of mid-1979. All costs are expressed in Hong Kong dollars, and the detailed report provides the basis for developing unit cost estimates for each line item. The costs summarized below are divided into three discrete phases:
•
•
•
Phase la is the initial runway, taxiway, and
facilities.
all related support
Phase Ib is the additional fill south of the immediate environs of the airport in Tung Chung Bay,
Phase II is the second runway, taxiway system and related support facilities.
Costs have been subdivided into those that traditionally accrue to the airport account and those that are normally the responsibility of tenants or the Government. These cost elements have been totalled to indicate the full
commitment of Hong Kong resources required to im- plement a replacement airport programme. In 1979 Hong Kong dollars, this commitment would be about HK $9.6 thousand million, excluding credits for salvage of land and facilities now used for other purposes.
HK$ (million)
Airport
Task
Account Tenants" Total
a
Phase la
Single-runway airport
5,508
1,539 7,047
Phase Ib
Tung Chung
Bay adjacent to
airport
269
269
Phase II
Two-runway
airport
1,749
578
2,327
Grand Total
7,257
2,386
9,643
а
Tenants include government facilities not directly related to airport operations.
38
AVP PARSONS OVERSEAS COMPANY WILMERSMITH & ASSOCIATES
*GOLLENS MELVIN WARD PARTNERSHIP
►CIVIL, AVIATION AUTHORITY (UK)
* WILBUR SMITH & ASSOCIATES
*COLLINS MELVIN WARD PARTNERSHIP
*CIVIL
APPENDIX A
BROAD TERMS OF REFERENCE
To review and update traffic forecasts.
• To confirm the feasibility of constructing and operat- ing an international airport on the Chek Lap Kok site to meet the forecast demand to 1995 and as far beyond that time as can reasonably be expected.
•
•
To prepare a pilot scheme, construction programme and costs for developing such an airport.
To recommend further studies where needed.