CONSTRUCTION COSTS

The Consultants have developed cost estimates for constructing the replacement airport based on prices prevailing as of mid-1979. All costs are expressed in Hong Kong dollars, and the detailed report provides the basis for developing unit cost estimates for each line item. The costs summarized below are divided into three discrete phases:

Phase la is the initial runway, taxiway, and

facilities.

all related support

Phase Ib is the additional fill south of the immediate environs of the airport in Tung Chung Bay,

Phase II is the second runway, taxiway system and related support facilities.

Costs have been subdivided into those that traditionally accrue to the airport account and those that are normally the responsibility of tenants or the Government. These cost elements have been totalled to indicate the full

commitment of Hong Kong resources required to im- plement a replacement airport programme. In 1979 Hong Kong dollars, this commitment would be about HK $9.6 thousand million, excluding credits for salvage of land and facilities now used for other purposes.

HK$ (million)

Airport

Task

Account Tenants" Total

a

Phase la

Single-runway airport

5,508

1,539 7,047

Phase Ib

Tung Chung

Bay adjacent to

airport

269

269

Phase II

Two-runway

airport

1,749

578

2,327

Grand Total

7,257

2,386

9,643

а

Tenants include government facilities not directly related to airport operations.

38

AVP PARSONS OVERSEAS COMPANY WILMERSMITH & ASSOCIATES

*GOLLENS MELVIN WARD PARTNERSHIP

►CIVIL, AVIATION AUTHORITY (UK)

* WILBUR SMITH & ASSOCIATES

*COLLINS MELVIN WARD PARTNERSHIP

*CIVIL

APPENDIX A

BROAD TERMS OF REFERENCE

To review and update traffic forecasts.

• To confirm the feasibility of constructing and operat- ing an international airport on the Chek Lap Kok site to meet the forecast demand to 1995 and as far beyond that time as can reasonably be expected.

To prepare a pilot scheme, construction programme and costs for developing such an airport.

To recommend further studies where needed.