In any case where the claimant has failed to supply further particulars required by the Director in accordance with subsection (4) the Lands Tribunal may on the hearing of the claim consider the merits

of the Director's request for further particulars, and the claimant's failure to supply them and may, if it thinks fit

-

(a) order the claimant to furnish some or all of such

particulars; and

(b) adjourn the hearing until the order is complied

with and the particulars are considered by the Director; and

(c) make such further order as it thinks fit as to

the costs of either party occasioned by the Director's request for and the claimant's failure to supply the further particulars.