TNAG-0740-FCO40-944-Quarterly-progress-reports-from-Hong-Kong-1978 — Page 91

FCO40 Hong Kong Department Records 聯邦事務部香港部檔案 All

CONFIDENTIAL * *

I

2

Subject

Furpose

3. N.T. Trunk Road To provide a new road

Additional Water To expand the oxirting Supply from Bast cumping and piping River

Stage II facilities to receive additional water from China

5. MR Extension

(a) Resumptions

to Tsuen Wan

(b) Village Removals

Phase I

Progress made and present position

proposed that the section of Trunk Road at Pak Sek Kok Bay be re-aligned. Final decision awaited.

Resumption/clearance of four connected borrow areas is

required.

(a) Borrow area at Chinese University (130,000 sq.ft.).

Resumption of land is in progress.

(b) Torrow area at Whitehead (180,000 sq.ft.). Resumption is

being processed.

(c) Borrow area at St. Christopher's Home (7,000 sq.ft.) (d) Borrow area A clearance of the site required.

Resumption gazetted on 7.7.78. Land will revert to the Crown on 11th August construction work will start end of August.

Next Quarter Targets

(i) Finalization of

alignment in

Phase I.

(ii) Submission of

resumption papers for Phase 11.

Resumption of land to continue.

Clearance of temporary structures (150 houses from River Indus Fumping Station to Ma Moi Ha.

Continue resumptions

Resumptions in North Tsuen Wan proceeding according to plan.

Negotiations continue with villagers most terms now agreed. Continue negotiations

and process resite house details.

CONFIDENTIAL

/ 3.....