TNAG-0740-FCO40-944-Quarterly-progress-reports-from-Hong-Kong-1978 — Page 7

FCO40 Hong Kong Department Records 聯邦事務部香港部檔案 All

Part I (Contd.)

Subject

Purpose

(c) MTRC depot

Site

-3-

Progress made and present position

Clearances for the depot site continued satisfactorily. About 30% of the Sai Lau Kok flat owners agreed to flats surveys for valuation and rehousing.

(d) Factory

clearances

Most operators in recent clearances have removed on time.

Next Cuarter

Targets

Land clearances for depot to be completed.

Persuade owners to agree to surveys and accept compen- sation, even after reversion on 12th November.

To maintain fact- ory removals target.

CONFIDENTIAL ##

5.Tai Po Ind-

Land for special ustrial Estate; land-intensive

industries in Hong Kong

| Ting Kok Road are underway. Clearance of Borrow Areas for Stage II Phase Two is substantially completed.

Commencement of

Stage II Phase One reclamation, construct- ion of Service Reservoir and Improvement of Stage II Phase

Two reclamation.

6.Sha Tin Tai New Trunk Road

Po Coastal Road

Phase I. The consulting Engineer has prod- uced a report on the Pak Shek Kok Bay Reclamation. Approval to the suggested alignment awaited.

Phase Two Resumption papers submitted to S for E

(i) Submission of

Resumption papers.

(ii) Site clear-

ance and resumption

Construction work for both phases now scheduled for early 1979.

GF 323

機密

CONFIDENTIAL