Part I (Contd.)
Subject
Purpose
(c) MTRC depot
Site
-3-
Progress made and present position
Clearances for the depot site continued satisfactorily. About 30% of the Sai Lau Kok flat owners agreed to flats surveys for valuation and rehousing.
(d) Factory
clearances
Most operators in recent clearances have removed on time.
Next Cuarter
Targets
Land clearances for depot to be completed.
Persuade owners to agree to surveys and accept compen- sation, even after reversion on 12th November.
To maintain fact- ory removals target.
CONFIDENTIAL ##
密
5.Tai Po Ind-
Land for special ustrial Estate; land-intensive
industries in Hong Kong
| Ting Kok Road are underway. Clearance of Borrow Areas for Stage II Phase Two is substantially completed.
Commencement of
Stage II Phase One reclamation, construct- ion of Service Reservoir and Improvement of Stage II Phase
Two reclamation.
6.Sha Tin Tai New Trunk Road
Po Coastal Road
Phase I. The consulting Engineer has prod- uced a report on the Pak Shek Kok Bay Reclamation. Approval to the suggested alignment awaited.
Phase Two Resumption papers submitted to S for E
(i) Submission of
Resumption papers.
(ii) Site clear-
ance and resumption
Construction work for both phases now scheduled for early 1979.