Appendix D
UNIVERSITY & POLYTECHNIC GRANTS COMMITTEE
Medical Sub-committee Report
Summary of approximate order of capital and recurrent
costs for Phase I of a phased development of CUHK Medical School
(Note : These are estimated orders of cost at January 1974
prices and not verified requirements).
Capital
Item
Government
$
University
$
Total $
Hospital
50m.
10m.
60m.
Polyclinic
9m.
9m.
Quarters
Senior
5m.
2.5m.
7.5m.
General
13m.
13m.
Menial
2m.
2 m.
Piling
8m.
2m.
10m.
Pre-clinical
8m.
8m.
Equipment
Hospital
10m.
2.5m.
12.5m.
Polydinic
3m.
3m.
Pre-clinical
1.5m.
1.5m.
Quarters
2.5m.
0.25m.
2.75m.
Fees
0.65m.
0.65m.
Totals
$102.5m.
$27.4m.
$129.9m.
Say
$103m.
$27m.
$130m.
(Estimated cost
of full unphased
$159 m.
$41m.
$200m.
development
.../2