Piling took six months, structural work 24 months and finishing and in- terior work a further seven months. Construction started in January 1967 and was completed in February 1970.
Contractors
Main contractors were: The Con- crete Product and Aggregate Co. Ltd. piling; Ohbayashi-Gumi Ltd. structure; and The Dusit Thani Con- struction Section - finishes.
-
-
Sub-contractors and suppliers in-
cluded:
Trane Equipments Suppliers & Co. -air-conditioning
Allied Engineering Co. Ltd. – air- conditioning installation
Sirivivatn Ltd. · electrical installa-
tions
Lee Kum Sia Co. Ltd. - plumbing Otis Elevator Co. lifts and es- calators
―
C. Itoh & Co. and Klockner hardware
Kuppsersbusch
ment
-
kitchen equip-
Faithful Engineering Co. dry
cleaning and laundry equipment
ITT - telephones
Kohler Co. - sanitary fixtures Meidensha Co. electrical equip-
ment.
―
Hotel tower from banquet hall terrace
Tiara roof-top restaurant
Far East BUILDER, September 1970
31