February_1968 — Page 24

Far East Builder 遠東建築雜誌 All

FREE = RRIF = 2000 = 'BERE

Main building with treaty room on left

Annexe

The annexe is three storeys high and maintains externally the same expres- sion as for the main office block. All concrete work, including that of the other buildings, was cast in situ using timber shuttering and scaffolding.

Contractors

The contractors were Ng Goon Han Constructions Co. Ltd. for the main building, and Siah Bros. Trading Co. for the annexe.

Sub-contractors and suppliers in-

cluded:

Strongroom doors and safes: Sime

Darby (M) Ltd.

Aluminium doors and fins: main building-China Engineers Ltd.: annexe-Diethelm & Co. Ltd. Malco Aluminium Works. Galvanised metal windows: main building-Sime Darby (M) Ltd.; annexe-William Jacks & Co. (M) Ltd.

Fibrous plaster board ceiling:

Brady's (M) Ltd.

Air conditioning installation: Sime

Darby (M) Ltd.

Electrical installation: Hwa Fong &

Co. Ltd.

Lifts: main building-China En- gineers Ltd.; annexe- -Paterson Simon & Co. (M) Ltd. Fire-fighting equipment: McAlister

& Co. Ltd.

Spread-acoustic

plaster

ceiling:

Brady's (M) Ltd. Aluminium flag poles: Diethlem &

Co. Ltd.

Waterpump and incinerator: Alli- ance (M) Engineering Co. Ltd.

39933.3

99933.

Internal courtyard in the main office block

42

Far East Architect & Builder February, 1968